Plan Review Notes
Plan Review Notes For Project Z22040014
Project Number Z22040014
Review Stop Z
Sequence Number 1
Notes
Date Text
2022-05-12 12:41:22CASE NO. FSPR 22-05
 TRANSIT VILLAGE 2022
 150 CLEARWATER DRIVE
  
 - CONTACT CHRIS KIMMERLY @ (561) 822-1426,
 [email protected]
 - OR ERIC SCHNEIDER @ (561) 822-1446,
 [email protected]
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF THREE
 (3) PAPER COPIES AND AN ELECTRONIC COPY IN .PNG AND
 .PDF FORMAT OF ALL PLANS. PLEASE NOTE THAT CHANGES ON
 THE RESUBMITTED PLANS OR THE SUBMITTAL OF
 INFORMATION/PLANS TO ADDRESS THE COMMENTS MAY RESULT IN
 ADDITIONAL COMMENTS.
  
 - THE PPRC COMMENTS SHALL BE SUFFICIENTLY ADDRESSED AND
 SUBMITTED TO THE PLANNING DIVISION BY 5 PM ON FRIDAY,
 05/27/22, TO BE ELIGIBLE TO BE SCHEDULED FOR THE
 7/13/22 DOWNTOWN ACTION COMMITTEE MEETING.
  
 - PLEASE NOTE THAT IF THE PLANNING DIVISION HAS NOT
 RECEIVED A RESPONSE TO THE PPRC COMMENTS WITHIN 60 DAYS
 FROM THE DATE OF THE PPRC MEETING (BY AUGUST 12, 2022),
 THE PLANNING DIVISION MAY NOTIFY THE APPLICANT THAT THE
 CASE IS CONSIDERED WITHDRAWN. ANY FURTHER ACTION SHALL
 REQUIRE A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($500).
  
 1. THIS PROPOSED PROJECT IS SIGNIFICANTLY DIFFERENT
 THAN THE CURRENTLY APPROVED SITE PLAN; THEREFORE, IT IS
 NOT A ?MODIFICATION TO THE EXISTING APPROVED SITE PLAN?
 AS STATED IN THE JUSTIFICATION STATEMENT, BUT RATHER A
 NEW SITE PLAN APPROVAL. THE PREVIOUSLY APPROVED SITE
 PLAN AND THE VARIANCES THAT WERE GRANTED DO NOT
 AUTOMATICALLY APPLY TO THE NEW SITE PLAN. ANY VARIANCES
 THAT ARE REQUIRED BASED ON THE NEW BUILDING DESIGN AND
 SITE LAYOUT REQUIRE APPROVAL BY THE DOWNTOWN ACTION
 COMMITTEE THROUGH THE VARIANCE PROCESS.
  
 2. STAFF HAS NOTED THAT THE PROPOSED SITE PLAN,
 INCLUDING THE USE MIX, DIFFERS FROM THE AGREEMENT FOR
 PURCHASE AND SALE DATED AUGUST 12, 2012. SINCE THE
 AGREEMENT FOR PURCHASE AND SALE ESTABLISHES THAT
 MODIFICATIONS ARE PERMITTED, SUBJECT TO PALM BEACH
 COUNTY APPROVAL, PLEASE PROVIDE THE LATEST AMENDMENT OR
 VERSION OF THE AGREEMENT FOR PURCHASE AND SALE THAT
 AUTHORIZES THE CHANGES PRESENTED IN THE CURRENT
 SUBMITTAL, INCLUDING, BUT NOT LIMITED TO:
  
 A. THE REDUCTION IN THE REQUIRED 40 PARKING SPACES FOR
 SFTRA/COUNTY STAFF AND 250 SFRTA PATRON PARKING SPACES
 (TOTAL 290 PARKING SPACES) TO 275 PARKING SPACES FOR
 THESE USERS.
 B. THE REMOVAL OF LEARNING CENTER/CULTURAL/EDUCATION
 USES FROM THE PROJECT.
 C. THE JUSTIFICATION STATEMENT SITE DATA TABLE LISTS 42
 WORKFORCE HOUSING UNITS AS BEING REQUIRED, WHILE THE
 AGREEMENT FOR PURCHASE AND SALE ONLY REQUIRES 38. THE
 PLANS DO NOT PROVIDE A BREAKDOWN TO VERIFY COMPLIANCE
 WITH EITHER NUMBER.
 D. SECTION 3E OF EXHIBIT D TRAFFIC CIRCULATION PLAN OF
 THE AGREEMENT FOR PURCHASE AND SALE LIMITS THE NUMBER
 OF PARKING SPACES WITHIN THE PARKING GARAGE TO THE 290
 PUBLIC USE PARKING SPACES AND, ??PROVIDE NOT MORE THAN
 THE NUMBER OF PARKING SPACES REQUIRED BY THE CITY OF
 WEST PALM BEACH FOR THE MIX OF USES AND
 INTENSITIES/DENSITIES?AS ACTUALLY CONSTRUCTED??. AS
 WILL BE SHOWN LATER IN THESE COMMENTS, THE PROJECT
 EXCEEDS THIS STANDARD.
  
 3. THE SITE CURRENTLY CONSISTS OF A PBC PARCEL AND AN
 SFTRA PARCEL.
 A. THE DECKS, COLUMNS AND A PORTION OF THE RETAIL
 BUILDING ON THE SOUTH END OF THE SECOND FLOOR CROSS
 THIS PARCEL LINE, WHICH CREATE SETBACK AND BUILDING
 SEPARATION ISSUES THAT NEED TO BE ADDRESSED.
 B. THE AGREEMENT FOR PURCHASE AND SALE INDICATES THAT
 PALM BEACH COUNTY WILL RETAIN OWNERSHIP OF THE
 INTERMODAL TRANSIT CENTER TO A POINT 21 FEET IN THE
 AIR. THE APPLICATION DOES NOT MENTION HOW THIS PROPOSED
 SUBDIVISION WILL OCCUR.
 C. THE JUSTIFICATION STATEMENT INDICATES THAT THE
 AGREEMENT FOR PURCHASE AND SALE INCLUDES THE SFRTA, YET
 THEY ARE NOT SHOWN AS A PARTY TO STAFF?S COPY OF THE
 AGREEMENT. WILL THE SFRTA RETAIN ANY OWNERSHIP AND IF
 SO, HOW WILL THE PARCEL BE SUBDIVIDED?
  
 4. TRANSIT VILLAGE BOUNDARY DIAGRAM SHEET A0-03
 DIFFERENT FROM THE ?ITC PROPERTY MAP? AND ?REQUIRED
 MODIFICATIONS FROM ORIGINAL APPROVAL IN OCT. 2011.
 CLEARLY SHOW THE ITC BOUNDARY ON THE GROUND LEVEL AND
 SECOND LEVEL OF THE VARIOUS PLANS.
  
 5. THERE ARE NUMEROUS UTILITY AND OTHER EASEMENTS SHOWN
 ON THE SURVEY. ALL OF THESE EASEMENTS MUST BE SHOWN ON
 THE SITE AND LANDSCAPE PLANS (GROUND LEVEL AND SECOND
 LEVEL) TO SHOW THAT THERE IS NO CONFLICT WITH THE
 PROPOSED DEVELOPMENT.
  
 6. PLEASE DOCUMENT AND IDENTIFY ALL REQUESTED VARIANCES
 AND WAIVERS FOR THE PROPOSED SITE PLANS.
  
 7. PLEASE PROVIDE AN UPDATED SURVEY CLEARLY DOCUMENTING
 THE CHANGES INCORPORATED AS PART OF THE RECENT BANYAN
 BOULEVARD STREETSCAPE PROJECT. ALL PLAN SHEETS MUST
 REFLECT THE ACCURATE BANYAN STREET CONFIGURATION. THIS
 IS CURRENTLY NOT REFLECTED ON ANY OF THE SUBMITTED PLAN
 SHEETS.
 A. PROPOSED RESIDENTIAL ON-STREET DROP OFF ON BANYAN
 FRONTAGE NOT PERMITTED WITHIN TOD-25 DISTRICT.
  
 8. SETBACKS ARE MEASURED FROM THE BACK OF CURB, NOT
 FROM THE PROPERTY LINE.
 A. SETBACK ON BANYAN (GROUND ? 5) IS 16? MIN. AND 50?
 MAX. (AVENUE-CLASSIFICATION) CONDITIONAL SETBACK FOR
 PARKING ABOVE 5TH STORY IS 31? MIN.
 B. SETBACK ON CLEARWATER (GROUND ? 5) IS 12? MIN. AND
 60? MAX. (SECONDARY-CLASSIFICATION) CONDITIONAL SETBACK
 FOR PARKING ABOVE 5TH STORY IS 27? MIN.
 C. ABUTTING CSX IS 15? MIN.
 D. REAR 5? MIN.
 E. SIDE INTERIOR 0? OR NFPA
 F. SETBACKS INTERNAL TO THE PROPERTY BETWEEN COUNTY
 ITC, SFRTA, AND APPLICANT?S PROPERTIES WARRANT FURTHER
 DISCUSSION. AS PREVIOUSLY STATED, THE PROJECT SITE IS
 SPLIT BETWEEN 2 SEPARATE PARCELS, AND POTENTIAL
 VERTICAL SUBDIVISION.
 9. PARKING: THE PARKING TABLE NEEDS TO BE CORRECTED TO
 BETTER CONVEY THE PARKING COUNTS. PLEASE NOTE, WHILE
 NOT MANDATORY, STAFF HAS INCLUDED THE ADDITIONAL
 ALLOWED 25% TOD PARKING SPACE REDUCTION.
 A. OFFICE: MIN. 2.5/1000SF = 457 SPACES (MAX. 4/1000SF
 = 731 SPACES) AFTER 25% TOD REDUCTION, 343 REQUIRED;
 PROVIDING 365 SPACES
 B. HOTEL: MIN. 1/4ROOMS = 27 SPACES, 1/800 SF = 11
 SPACES (MAX. 1/ROOM = 108 SPACES, 1/400 SF = 23
 SPACES); AFTER 25% TOD REDUCTION, 29 REQUIRED;
 PROVIDING 38 SPACES
 C. COMMERCIAL: MIN. 2/1000 SF = 110 SPACES (MAX. 4/1000
 SF = 219 SPACES) AFTER 25% TOD REDUCTION, 83 REQUIRED;
 PROVIDING 110 SPACES
 D. RESIDENTIAL: MIN. 1/UNIT = 821 SPACE, 1/20 GUEST =
 41 GUEST (MAX. 2/UNIT = 1,642 SPACES, 41 GUEST) AFTER
 25% TOD REDUCTION, 661 REQUIRED; PROVIDING 896 SPACES
 TOTAL, NEED A CLEARER BREAKDOWN.
 E. MICRO-UNITS: MIN. 0/UNIT (MAX. 0.5/UNIT = 83 SPACES,
 1/20 GUEST = 8 SPACES); PROVIDING? NEED CLEARER
 BREAKDOWN.
 F. LIVE/WORK UNITS: MIN. 2/1000 SF = 534 SPACES (MAX.
 4/1000SF = 1068 SPACES); AFTER 25% TOD REDUCTION, 400
 REQUIRED; PROVIDING? NEED CLEARER BREAKDOWN. ALSO THERE
 ARE A TOTAL OF 12 LIVE/WORK UNITS FOR 267,000 SF,
 ASSUMING ~22,250 SF EACH? PLEASE EXPLAIN THESE UNITS.
 G. SFRTA AND ITC PARKING: MIN. 290 SPACES (250 FOR
 SFRTA PATRONS AND 40 FOR SFRTA/COUNTY); PROVIDING 275?
 WHY THE SHORTAGE OF 15 SPACES PER THE PSA?
 H. TOTAL MIN REQUIRED: 1,467 SPACES (WITHOUT ANY FOR
 MICRO-UNITS AND NOT INCLUDING 534 FOR LIVE/WORK) 2001
 WITH LIVE/WORK INCLUDED; 2,291 WITH SFRTA/ITC PARKING.
 NOT COUNTING 25% REDUCTION. PROVIDING 2,003 SPACES WITH
 319 UNALLOCATED. EXPLAIN THE UNALLOCATED.
 I. BIKE PARKING: MIN. 1/15 COMMERCIAL/HOTEL/OFFICE = 40
 SPACES REQUIRED, 1/15 RESIDENTIAL = 57 SPACES REQUIRED,
 ALSO NEED TO PROVIDE A SHOWER/CHANGING FACILITY WITHIN
 200 FT. OF BUILDING ENTRANCE. PROVIDING 116 COMMERCIAL,
 100 RESIDENTIAL.
 I. PROVIDE SECURE RESIDENT BICYCLE ROOMS. PROVIDE
 NON-RESIDENTIAL COVERED BICYCLE PARKING AREAS
 DISTRIBUTED THROUGHOUT THE SITE. PROVIDE THE DIMENSIONS
 FOR THE BICYCLE PARKING AREAS ON THE PLANS.
 II. WHERE ARE THE SHOWER/CHANGING FACILITIES LOCATED?
 J. IN THOSE CASES WHERE THE SIDE OF ANY PARKING STALL
 IS ADJACENT TO A WALL, FENCE, BUILDING, OR OTHER
 PHYSICAL OBSTRUCTION, THE STALL WIDTHS SHALL BE
 INCREASED BY A MINIMUM OF ONE FOOT. WHERE THERE IS AN
 OBSTRUCTION ON BOTH SIDES OF THE STALL, THE STALL
 WIDTHS SHALL BE INCREASED BY A MINIMUM OF TWO FEET.
 III. PARKING GARAGE HAS INSTANCES WHERE PARKING SPACES
 APPEAR TO BE NEXT TO WALLS OR STRUCTURE.
 IV. ADA PARKING SPACES ARE LOCATED IN INEFFICIENT AND
 NOT OPTIMAL AREAS. ALL SPACES SHALL HAVE ACCESS TO A
 CURB RAMP OR CURB CUT, WHEN NECESSARY, TO ALLOW
 ENTRANCE TO THE BUILDING SERVED. SPACES SHALL BE
 LOCATED SO THAT USERS ARE NOT COMPELLED TO WALK OR
 OTHERWISE MOVE BEHIND PARKED VEHICLES, EXCLUDING OTHER
 VEHICLES PARKED IN ADJACENT PARKING SPACES FOR THE
 DISABLED.
 V. PLEASE PROVIDE PARKING PAINTED STRIPING DETAILS THAT
 MEET THE CITY STANDARDS OF SEC. 94-485.
 VI. PLEASE PROVIDE ALL PARKING DIMENSIONS FOR DRIVE
 AISLE, PARKING RAMP SLOPE, PARKING STALLS, ETC.
 K. PARKING STRUCTURE RAMP SLOPES: INTERNAL RAMPS APPEAR
 15.8% AND 12.4%. PER SEC. 94-111 (Q.)(2.) IF THE RAMP
 IS GREATER THAN 14 PERCENT, A BREAK-OVER TRANSITION
 SHALL BE REQUIRED.
 L. INTERNAL PARKING STRUCTURE POSES CONCERNS WITH
 INGRESS/EGRESS OF RESIDENTS, EMPLOYEES, VISITORS, AND
 THE OPERATIONS OF LOADING AND BICYCLE USERS. LOADING
 SPACES AND BAYS ARE INEFFICIENT AND CAUSE CONFLICT
 ZONES/SAFETY CONCERNS. POTENTIAL SPILLBACK AND QUEUING
 ISSUES ONTO CLEARWATER.
 M. THE PARKING GARAGE SHOULD BE PREWIRED FOR EV
 CHARGERS BOTH FOR RESIDENTS AND CUSTOMERS. THE
 ELECTRICAL ROOMS NEED TO BE PROVIDED WITH SUFFICIENT
 SPACE TO ACCOMMODATE THE REQUIRED ELECTRICAL PANELS AND
 AREAS NEED TO BE DESIGNATED FOR THE TRANSFORMERS.
  
 10. CURB-CUTS AND PASSENGER LOAD/DROP-OFF: PER SEC.
 94-111 TABLE IV-11 ? TOD DOES NOT PERMIT ON-STREET
 AND/OR PASSENGER DROP-OFF OR LOADING ON AVENUE
 (BANYAN).
  
 11. PLEASE PROVIDE AN FAR AND GBA DIAGRAM SHOWING THE
 BREAKDOWN OF THE PROJECT?S COUNTED/UNCOUNTED ROOMS AND
 SPACES.
 A. GROSS BUILDING AREA MEANS THE TOTAL FLOOR AREA OF A
 BUILDING, INCLUDING AIR-CONDITIONED OR FULLY ENCLOSED
 STORAGE SPACES, ENCLOSED AREAS ON THE ROOFTOP, SUCH AS
 BATHROOMS AND LOBBIES, STAIRS AND ELEVATOR AREAS, AND
 EXTERNAL UNENCLOSED CIRCULATION AREAS. THE GROSS
 BUILDING AREA DOES NOT INCLUDE PARKING AREAS;
 UNENCLOSED COLONNADES, PORCHES AND BALCONIES;
 MECHANICAL AND ELECTRICAL SPACES; AND TRASH ROOMS.
 STORAGE SPACES WITHOUT WINDOWS AND ENCLOSED BY SURFACES
 THAT ALLOW FOR NATURAL VENTILATION OR OUTSIDE AIR
 CIRCULATION SHALL NOT BE INCLUDED.
 VII. GROSS BUILDING AREA REQUIREMENTS:
 1. ANY PORTION OF THE PARKING AREA WHICH EXCEEDS THE
 MAXIMUM PARKING RATIO SHALL BE INCLUDED IN THE
 CALCULATIONS OF GROSS BUILDING AREA. THIS SHALL INCLUDE
 STALLS AND ALL ASSOCIATED CIRCULATION AREAS.
 2. PARKING LOCATED BELOW GRADE SHALL NOT BE COUNTED AS
 PART OF THE GROSS BUILDING AREA.
 3. THE GROSS BUILDING AREA SHALL BE MEASURED FROM THE
 OUTSIDE FACE OF EXTERIOR WALLS.
  
 12. PLEASE PROVIDE ACTIVE USE DIAGRAM AND CALCULATIONS
 FOR SITE FRONTAGES.
  
 13. IT APPEARS THAT THE ELEVATION DRAWINGS DO NOT MATCH
 THE GROUND LEVEL SITE PLAN. THE ELEVATION DRAWINGS MUST
 INCLUDE HORIZONTAL DIMENSIONS FOR THE VARIOUS FEATURES
 SO THAT STAFF CAN VERIFY THAT THE ELEVATIONS MATCH THE
 SITE PLAN BUT ALSO THAT THE SITE FRONTAGES COMPLY WITH
 THE VARIOUS ZONING REQUIREMENTS.
  
 14. PLEASE SPECIFY THE TYPE OF OPEN SPACES (PRIVATE &
 PUBLIC) PROVIDED ON THE DRAWINGS, REFERENCE SEC. 94-109
 AND TABLE IV-7. CLARIFY HOW THE REQUIREMENTS OF EACH
 OPEN SPACE TYPE IS MET WITHIN THE LANDSCAPE DRAWINGS.
 A. PROPOSED OPEN SPACE AT THE SOUTHERN TRIANGLE OF THE
 SITE DOES NOT MEET PUBLIC OR PRIVATE OPEN SPACE
 TYPOLOGY DUE TO LACK OF ABUTMENT TO AN ACTIVE USE.
 B. THE PUBLIC OPEN SPACE SHOWN ON THE SECOND LEVEL
 REQUIRES THE APPROVAL OF A VARIANCE, SIMILAR TO THE ONE
 APPROVED AS PART OF THE CURRENTLY APPROVED SITE PLAN.
  
 15. STREET TREES: STREET TREES SHALL BE PLANTED AT 30
 FT. INTERVALS ALONG EACH STREET FRONTAGE. CLEARWATER
 FRONTAGE SHOULD HAVE APPROX. 46 TREES AND BANYAN
 FRONTAGE APPROX. 13.
  
 16. PROPOSED RESIDENTIAL DROP-OFF AND LOOP FOR
 RESIDENTIAL TOWER ON CLEARWATER IS OUTSIDE OF PROPERTY
 LINES AND ENCROACHES INTO CITY ROW. ADDITIONAL SMALLER
 DROP-OFF ADJACENT TO LOADING BAY/BACK-OF-HOUSE. WHY ARE
 THESE DROP-OFF SPACES NEEDED FOR THE RESIDENTIAL TOWER?
 ADJACENT HOTEL/OFFICE ALSO INCLUDES A SMALL DROP-OFF,
 PRESENTS STACKING/QUEUING ISSUES AND SPILL OVER INTO
 CLEARWATER. STAFF DOES NOT SUPPORT THE RESIDENTIAL
 DROP-OFF ROAD ADJACENT TO RESIDENTIAL TOWER/CLEARWATER
 PROPOSED RESIDENTIAL DROP-OFF NOT IN COMPLIANCE.
 ENCROACHES INTO THE PUBLIC RIGHT-OF-WAY AND PER SEC.
 94-111 (N.)(3.) DESIGNATED PASSENGER LOADING AND
 DROP-OFF AREAS SHALL BE SET BACK A MINIMUM OF 16 FEET
 FROM THE BACK OF CURB, SHALL BE SEPARATED FROM THE
 SIDEWALK BY A 5-FOOT-WIDE LANDSCAPE BUFFER AND SHALL BE
 SUBJECT TO APPROVAL BY THE CITY TRAFFIC ENGINEER. PORTE
 COCHERES ARE SUBJECT TO MINIMUM STANDARDS DEPENDING ON
 SUBDISTRICT LOCATION AND ADJACENCY TO A STREET
 DESIGNATION AND ARE SEPARATED INTO TWO TYPES WHICH ARE
 ILLUSTRATED IN FIGURE IV-22. ONLY A TYPE A PORTE
 COCHERE IS ALLOWED IN THE TOD-25 SUBDISTRICT.
 A. INSTEAD, THE BUILDING FRONT SHOULD BE MOVED CLOSER
 TO CLEARWATER, AND RECONFIGURE LOADING AND
 BACK-OF-HOUSE TO INCLUDE THE DRIVEWAY AND DROP OFF
 AREA.
 B. SEE ABOVE: PROPOSED LOADING SPACE ON RESIDENTIAL
 TOWER DOES NOT FUNCTION FOR VEHICULAR MOVEMENT.
  
 17. ITC BUS LOOP IS NOW ENTIRELY COVERED OVERHEAD BY
 PLAZA AND BUILDINGS/STRUCTURES. PREVIOUS DESIGN HAD AN
 OPEN-AIR CORRIDOR TO PROVIDE LIGHT, LANDSCAPING, AND
 VENTILATION/OPEN-AIR ACCESS. HOW WILL THE REMOVAL OF
 THESE ELEMENTS BE MITIGATED OR COMPENSATED FOR,
 ESPECIALLY WHERE ANY MECHANICAL VENTING WILL BE
 LOCATED?
  
 18. PLEASE PROVIDE SHEETS AND DRAWINGS IDENTIFYING HOW
 THE FA?ADE ARTICULATION REQUIREMENTS ARE MET FOR THE
 PROJECT. PLEASE REFERENCE SEC. 94-109 AND TABLE IV-4:
 FA?ADE ARCHITECTURAL REQUIREMENTS.
 A. ILLUSTRATE TRANSPARENCY CALCULATIONS, FENESTRATION
 CALCULATIONS, PLANAR BREAK CALCULATIONS, PROJECTIONS,
 ETC. FOR ALL BUILDING FACADES.
  
 19. PLEASE PROVIDE DETAILS AND MATERIALS OF THE GARAGE
 STRUCTURE, HOW IS IT BEING SCREENED, MATERIALS, PLANTS,
 ETC.
  
 20. REGARDING THE ARCHITECTURAL DESIGN OF THE TOWERS,
 HAS VARIED FACADES AND ELEMENTS BEEN EXPLORED OR IS
 THERE A REASON FOR UNVARIED/SIMILARLY DESIGNED TOWERS?
  
 21. REGARDING THE TOWERS AND OVERALL PROJECT HEIGHT,
 STAFF REQUESTS THAT THE BANYAN RESIDENTIAL TOWER IS THE
 TALLEST RATHER THAN THE CLEARWATER HOTEL/OFFICE TOWER.
 THIS IS BECAUSE BANYAN IS THE WIDEST ROADWAY AND IS
 MORE APPROPRIATELY FRAMED/CAN ACCOMMODATE THE TALLER
 MASS. ADDITIONALLY, STAFF RECOMMENDS THAT THE BANYAN
 RESIDENTIAL TOWER STEPS DOWN IN SOME CAPACITY TOWARD
 TAMARIND AVE. AS WAS APPROVED WITHIN THE ORIGINAL SITE
 PLAN. THIS GIVES RESPECT TO THE SCALE OF THE SEABOARD
 TRAIN STATION AND PUBLIC REALM ALONG TAMARIND.
  
 22. BE COGNIZANT THAT THE EDGE 2 BUILDING LOCATED AT
 300 CLEARWATER IS APPROVED AND UNDERGOING BUILDING
 PERMITTING PROCESS, THIS PROJECT?S INGRESS/EGRESS FROM
 DRIVES MAY PRESENT CONFLICT POINTS. THE GROUND LEVEL
 PLANS NEED TO SHOW THE EDGE 2 CURB CUTS IN ORDER FOR
 STAFF TO EVALUATE THE IMPACT OF THE ACCESS POINTS TO
 CLEARWATER. ADDITIONALLY, THE PEDESTRIAN CONNECTION
 FROM THE ?OASIS? PARK ELEMENT ACROSS CLEARWATER TO THE
 STAIRWELL/ELEVATOR FOR THE UPPER PLAZA WILL NEED
 RECONSIDERATION WITH THE INCOMING DEVELOPMENT.
  
 23. PLEASE CLARIFY GROUND FLOOR PEDESTRIAN CIRCULATION
 WITH ITC, ACCESSING UPPER PLAZA SPACES, AND INTERNAL
 CIRCULATION BETWEEN RETAIL AND RESIDENTIAL TOWERS. IS
 THE ITC BUS LOOP SEPARATED/CLOSED OFF IN THE EVENINGS
 WHEN BUS OPERATIONS HALT, HOW IS WAYFINDING ADDRESSED
 TO ACCESS THE UPPER PLAZA SPACES?
 A. THE ITC ADA PATH DRAWING SUBMITTED WITH THE
 APPLICATION SHOWS THE ADA ROUTE UTILIZING A CROSSWALK
 THAT IS DESIGNATED FOR REMOVAL.
 B. THE ITC FENCE EXHIBIT SHOWS THE FENCE AROUND THE
 OPEN SPACE AT THE SOUTH END OF THE SITE AS A ?PRIVATE
 PARK FENCE?. THIS DOES NOT MATCH THIS AS BEING DEPICTED
 AS PUBLIC OPEN SPACE ON OTHER PLANS.
  
 24. STAFF WILL BE RECOMMENDING PEDESTRIAN IMPROVEMENTS
 AND INCREASED ACCESSIBILITY TO TAMARIND AND THE
 DOWNTOWN AREA. AS A TOD PROJECT, YOU MUST DEMONSTRATE
 HOW THE RELATION AND CONNECTIVITY IS IMPROVED TO THESE
 CORRIDORS INTO THE DOWNTOWN. RECOMMEND POTENTIAL: WORK
 WITH SFRTA TO IMPLEMENT AT-GRADE CONNECTION(S) ACROSS
 RAILS TO TAMARIND. IMPROVE THE PEDESTRIAN BRIDGE
 CONNECTING SEABOARD TRAIN STATION AND TRANSIT VILLAGE
 PROJECT. EXPLORE CONCEPT OF ADDITIONAL PEDESTRIAN
 BRIDGES OR CONNECTIONS.
  
 25. PLEASE PROVIDE INFORMATION ON WHAT THE ?MOTOR
 LOBBY? IS.
  
 26. THE SOUTH RESIDENTIAL BUILDING IS NOT PERMITTED TO
 ENCROACH THE 20-FOOT FIRE DEPARTMENT ACCESS EASEMENT.
 NOTE: EVEN WITHOUT THE BUILDING ENCROACHMENT, THIS DOES
 NOT FUNCTION.
  
 27. PROVIDE TURNING DIAGRAMS FOR THE LOADING AREAS
 UNDER THE NORTH BUILDING, ENTRY POINTS TO THE SITE AND
 THE OTHER LOADING AREAS.
  
 28. WHERE ARE THE GENERATORS, TRANSFORMERS, AND OTHER
 MECHANICAL EQUIPMENT AND HOW ARE THEY SCREENED IN
 ACCORDANCE WITH CITY CODE REQUIREMENTS?
  
 29. PLEASE CONSIDER USING SUSTAINABLE INFRASTRUCTURE
 SUCH AS ROOFTOP SOLAR OR RAINWATER CAPTURE/REUSE
 CISTERNS.
  
 30. SHEET A6-01 SHOWS PUBLIC OPEN SPACES EXTENDING INTO
 THE BUS LANE.
  
 31. FOR THE EVENTUAL DOWNTOWN ACTION COMMITTEE (DAC)
 MEETING, PLEASE PROVIDE FULLY DETAILED RENDERINGS AND
 PERSPECTIVE DRAWINGS OF THE FINAL PROJECT.
 32. PROVIDE A PRELIMINARY CONSTRUCTION PLAN TO SHOW HOW
 THE SITE WILL BE DEVELOPED WHILE MAINTAINING ITC
 OPERATIONS, TO INCLUDE PARKING. ADDITIONALLY, PROVIDE
 THE PRELIMINARY PLAN FOR EMPLOYEE AND CONTRACTOR
 PARKING DURING CONSTRUCTION.
  
 33. THERE ARE COLUMN LOCATIONS THAT WHEN COMBINED WITH
 THE LOCATION OF THE PROPOSED ITC FENCE CREATE CHOKE
 POINTS FOR THE BUS PATRONS AS THEY CHANGE BETWEEN
 ROUTES. WHILE THEY ALL APPEAR TO COMPLY WITH ADA
 MINIMUMS, THEY DO NOT PROVIDE COMFORTABLE PEDESTRIAN
 WIDTHS FOR TWO USERS TO PASS SIDE-BY-SIDE. PLEASE
 REVIEW.
  
 34. THE SITE, LANDSCAPE AND CIVIL PLANS ALL NEED TO
 SHOW CONSISTENT, CODE COMPLIANT CONDITIONS.
  
 35. PROVIDE VERIFICATION THAT THE PROJECT MEETS THE
 STREETSCAPE REQUIREMENTS OF SECTION 94-113. THIS
 INCLUDES LIGHTING, SIDEWALK WIDTH, LANDSCAPE, BICYCLE
 PARKING, STREET FURNITURE, ETC.
  
 36. PROVIDE COMPLIANCE WITH SEC. 94-106 ? GENERAL USES
 WITH SPECIAL REQUIREMENTS (8.A) MICRO-UNITS (A.-F.)
 A. MICRO-UNIT MEANS A SMALL RESIDENTIAL UNIT WITH A
 TOTAL SQUARE FOOTAGE BETWEEN 300 SQUARE FEET AND 549
 SQUARE FEET, WITH A FULLY FUNCTIONING KITCHEN AND
 BATHROOM.
 B. SEC. 94-109 ?DWELLING UNIT REQUIREMENTS
 VIII. DWELLING UNITS SHALL NOT BE LESS THAN 550 SQUARE
 FEET. IN MULTIPLE DWELLING UNIT BUILDINGS, THE
 CUMULATIVE AVERAGE OF ALL DWELLING UNITS SHALL NOT BE
 LESS THAN 800 SQUARE FEET.
 IX. SMALLER DWELLING UNITS MAY BE ALLOWED AS
 MICRO-UNITS. THE CUMULATIVE AVERAGE SIZE MINIMUM SHALL
 NOT BE APPLICABLE TO MULTIPLE DWELLING UNIT BUILDINGS
 WHERE MICRO-UNITS COMPOSE A MINIMUM OF 80 PERCENT OF
 THE TOTAL NUMBER OF UNITS. IN ALL OTHER CASES, THE
 CUMULATIVE AVERAGE SIZE OF ALL DWELLING UNITS SHALL NOT
 INCLUDE THE MICRO-UNITS IN SUCH CALCULATION. SEE
 MICRO-UNITS.
  
  Print