| 2022-05-10 11:21:47 | TRAFFIC COMMENTS |
| | 1) PROVIDE ORIGINAL TRAFFIC STUDY INCLUSIVE OF THE |
| | REFERENCED EXHIBIT D |
| | 2) CONDUCT A FULL DETAILED TRAFFIC STUDY. ROADWAYS |
| | GEOMETRY AND NEARBY TRAFFIC CONDITIONS HAVE CHANGED |
| | SIGNIFICANTLY SINCE THE INITIAL SITE PLANS APPROVAL |
| | 3) DEPENDING ON THE OUTCOME OF THE TRAFFIC ANALYSIS, |
| | TDM MEASURES MAY NEED TO BE NEGOTIATED AND ESTABLISHED |
| | 4) PROVIDE COUNTY TPS LETTER |
| | 5) PROVIDE DETAILS PERTAINING THE TRANSITION FROM |
| | EXISTING TO FUTURE TRANSIT SERVICES, IN TERMS OF |
| | LOGISTICS AND OPERATIONS |
| | |
| | SITE COMMENTS |
| | 6) PROVIDE A SEPARATE SITE PLAN SHOWCASING ONLY BASIC |
| | TRANSPORTATION FEATURES AND THEIR DIMENSIONS. |
| | SPECIFICALLY: SIDEWALK, CURB, PARKING STALLS, |
| | CROSSINGS, WALKWAY, ROADWAY, DRIVE ISLES, DRIVEWAYS, |
| | PAVEMENT MARKINGS, SIGNAGE |
| | 7) ON THE SITE PLAN, PLEASE SHOWCASE BASIC CURB DETAILS |
| | (I.E. DRIVEWAY AND PARKING STALLS) ON THE OPPOSITE SIDE |
| | OF THE ROADS SURROUNDING THE PROPOSED DEVELOPMENT. |
| | PLEASE PROVIDE DOCUMENT NAME AND SHEET NUMBER |
| | SHOWCASING SUCH FEATURES. |
| | 8) PROVIDE AUTOTURN ANALYSIS FOR GARBAGE TRUCK AND/OR |
| | SERVICE VEHICLES DRIVING IN AND OUT OF THE PROPOSED |
| | DEVELOPMENT WITH VEHICLE DYNAMIC ENVELOPES CLEARLY |
| | DEFINED. ANALYSIS SHOULD BE PROVIDED IN A SEPARATE |
| | FILE/DRAWING. PLEASE PROVIDE DOCUMENT NAME AND SHEET |
| | NUMBER SHOWCASING THE ANALYSIS. |
| | |
| | VALERIO ORICCHIO |
| | CITY TRANSPORTATION ENGINEER |
| | 561-494-1092 |
| | [email protected] |
| | |
| |