| 2022-08-02 11:22:33 | |
| | |
| | IF DEVELOPMENT IS CHOOSING TO PROVIDE ART ON SITE TO |
| | SATISFY THE PUBLIC ART REQUIREMENT THEN POTENTIAL ART |
| | SITES MUST BE IDENTIFIED ON THE SITE PLAN. IF DEVELOPER |
| | IS CHOOSING TO CONTRIBUTE TO THE ART FUND, THEN PLEASE |
| | EMAIL [email protected] |
| | FOR SITE PLAN APPROVAL IT IS REQUIRED THAT EITHER |
| | CHOICE BE STATED CLEARLY. |
| | IF INTEGRATING ART ON THE SITE IT MUST BE IN AN OPEN, |
| | PUBLICLY ACCESSIBLE AREA, SUCH AS THE OPEN GRASS AREA |
| | ON THE DEVELOPMENT SITE. |
| | |
| | CONTACT SYBILLE WELTER |
| | [email protected] |
| | |
| 2022-05-12 11:36:12 | PROJECT IS SUBJECT TO PUBLIC ART REQUIREMENT |
| | PUBLIC ART REQUIREMENT: |
| | TOTAL CONSTRUCTION COSTS OF THIS DEVELOPMENT ARE OVER |
| | $500,000 IT IS SUBJECT TO THE PUBLIC ART REQUIREMENT AS |
| | PER CITY ORDINANCE. |
| | SECTION 78-129: ALL PRIVATE DEVELOPMENT PROJECTS, |
| | INCLUDING NEW CONSTRUCTION, OR THE RENOVATION OR |
| | IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL |
| | CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN |
| | $500,000 ARE SUBJECT TO THE PUBLIC ART REQUIREMENT. |
| | OPTION 1: INSTALL ARTWORK ON THE DEVELOPMENT SITE |
| | VALUED IN AN AMOUNT NOT LESS THAN ONE PERCENT OF THE |
| | TOTAL CONSTRUCTION COSTS; OR |
| | OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO 75 PERCENT OF |
| | ONE PERCENT OF THE TOTAL CONSTRUCTION COSTS FOR DEPOSIT |
| | TO THE PUBLIC ART ACCOUNT. |
| | A COMPLETED PUBLIC ART ASSESSMENT APPLICATION IS |
| | REQUIRED AT TIME OF BUILDING PERMIT SUBMITTAL. |
| | |
| | CONTACT SYBILLE WELTER, ADMINISTRATOR OF PUBLIC ART & |
| | CULTURE AT [email protected] TO OBTAIN AN ART ASSESSMENT |
| | APPLICATION AND REVIEW THE REQUIREMENTS. |
| | |
| |