| Date |
Text |
| 2022-04-14 10:05:53 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY'S OFFICIAL VERTICAL DATUM IS NGVD1929. THE |
| | CITY HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE |
| | CONVERSION EQUATION TO NGVD1929 AT THE PROJECT LOCATION |
| | IS PROVIDED. PROVIDE CONVERSION TO NGVD1929 ON THE |
| | SURVEY AND EVERY SHEET WITH ELEVATION INFORMATION. |
| | |
| | 2. SHOW AND LABEL STORM PIPE BETWEEN CATCH BASIN IN THE |
| | CUL-DE-SAC AND THE CANAL. |
| | |
| | 3. PROVIDE CROSS SECTIONS AT THE DRIVEWAY CONNECTIONS |
| | AT THE PROPERTY LINES. LABEL PROPERTY LINE AND SHOW |
| | GENERAL SURFACES ARE SLOPING AND WHERE THE HIGH POINT |
| | WILL BE WITHIN THE SITE. |
| | |
| | 4. PROVIDE CROSS SECTION FROM PALM BEACH LAKES BLVD TO |
| | INTERIOR OF VEHICLE STACKING AREA. |
| | |
| | 5. PROVIDE CROSS SECTION FROM OUTSIDE NORTHEAST |
| | PROPERTY LINE TO FACE OF BUILDING. DIMENSION DRIVE |
| | AISLE, PARKING, LANDSCAPING, ETC. |
| | |
| | 6. CAR WASH WASTEWATER IS NOT TO ENTER THE DRAINAGE |
| | SYSTEM. |
| | |
| | 7. THE CITY DOES NOT ALLOW THE USE OF ORIFICES WITH |
| | EXFILTRATION TRENCHES. |
| | |
| | 8. INCLUDE PRBS IN STRUCTURES CONNECTED TO EXFILTRATION |
| | TRENCHES TO EXTEND THE LIFE OF THE EXFILTRATION |
| | TRENCHES. |
| | |
| | 9. AVOID PLANTING TREES OVER UTILITY PIPES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH |
| | THE ENGINEERING PERMIT SUBMITTAL. |
| | |
| | 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF |
| | CONSTRUCTION, IF REQUIRED. |
| | |
| | 3. PROVIDE AN EROSION CONTROL PLAN WITH DETAILS. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | [email protected] |
| | |
| |