Plan Review Notes
Plan Review Notes For Project Z22020019
Project Number Z22020019
Review Stop STORM
Sequence Number 1
Notes
Date Text
2022-03-09 09:54:59THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. NGVD1929 TO NAVD1988 CONVERSION EQUATION IS
 DIFFERENT BETWEEN THE SURVEY AND THE ENGINEERING PLAN.
  
 2. REDUCE THE AMOUNT OF DRAINAGE PIPE IN THE RIGHT OF
 WAY BY CONNECTING TO THE EXISTING VALLEY GUTTER INLET
 BETWEEN THE ON-STREET PARKING SPACES.
  
 3. LABEL THE ONSITE DRAINAGE CONTROL STRUCTURE.
  
 4. THERE IS A PROPOSED FPL CHARGING STATION PROJECT ON
 THE SOUTH SIDE OF THE ALLEY. SHOW THE DRIVEWAY OPENING
 AND OTHER PROPOSED IMPROVEMENTS ALONG THE SOUTH R/W OF
 THE ALLEY FROM THAT PROJECT ON THE CONCEPTUAL
 ENGINEERING PLAN.
  
 5. REVIEW THE CITY?S PROPOSED UTILITY PROJECT IN THE
 ALLEY BETWEEN ROSEMARY AVE AND QUADRILLE PLAZA DRIVE.
  
 6. LABEL THE WEST RIGHT OF WAY LINE OF QUADRILLE PLAZA
 DRIVE.
  
 7. GARAGE OPENING TO BE OF SUFFICIENT HEIGHT FOR
 MAINTENANCE VEHICLES TO ACCESS THE DRAINAGE SYSTEM
 UNDER THE BUILDING.
  
 8. SHOW EXISTING AND PROPOSED UTILITIES ON THE
 LANDSCAPE PLANS.
  
 9. PROVIDE CROSS SECTIONS FROM SOUTH ALLEY RIGHT OF WAY
 TO FACE OF BUILDING AND TO 30 FEET INSIDE BUILDING AT
 THE DRIVEWAY. LABEL RIGHT OF WAY LINES AND PROVIDE
 DIMENSIONS FROM THE RIGHT OF WAY TO BUILDING FACE AND
 SHOW GENERAL SURFACE SLOPES.
  
 10. EXTRA SET OF DOORS SHOWN ON CONCEPTUAL ENGINEERING
 PLAN OPENING ON QUADRILLE PLAZA DRIVE.
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION, IF REQUIRED.
  
 3. PROVIDE AN EROSION CONTROL PLAN WITH DETAILS.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved