Plan Review Notes
Plan Review Notes For Project Z21120019
Project Number Z21120019
Review Stop ENG - PPRC
Sequence Number 2
Notes
Date Text
2022-03-28 11:16:22Z21120019 - 2112 TAMARIND RESUB 3.24.22
  
 COMMENTS FROM RICK ROSSANO, SR. PROJECT COORDINATOR,
 ENG. SERVICES DEPT., 561-494-1098 [email protected] :
  
 1. CONFIRM THAT A COMPLETED LOS ANALYSIS SUMMARY TABLE
 HAS BEEN SUBMITTED DIRECTLY TO ENGINEERING (SHEET 33 OF
 CITY OF WPB DEVELOPMENT APPLICATION).
 2. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 3. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER.
 4. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND
 STORMWATER PIPES ALONG ENTIRE PROJECT FRONTAGE.
 5. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED
 AREAS.
 6. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 1. FOR FORMAL ENGINEERING SUBMITTAL , PLANS SHALL SHOW
 PROPOSED LOCATIONS AND DIMENSIONS OF ALL WATER,
 STORMWATER, AND SANITARY AND SEWER LINES, INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, METERS, AND
 OTHERS DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. ALL
 AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE VIEW.
 DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN
 VIEW FOR ALL SANITARY AND STORM SEWERS. ADDITIONALLY,
 PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES LOCATED ON THE RIGHT-OF-WAY. PROVIDE PROFILE
 AND CLEARANCES AT ALL UTILITY CROSSINGS.
 7. PLEASE CLOUD/HIGHLIGHT PLAN REVISIONS OR CHANGES IN
 SCOPE FOR RESUBMITTAL OF DRAWINGS.
 8. FOR FORMAL ENGINEERING SUBMITTAL , CUT AND CAP
 UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY
 LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY.
 9. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE DEDICATED
 UTILITY EASEMENTS TO ALLOW ACCESS FOR CITY PERSONNEL TO
 PROPOSED UTILITY WATER METERS.
 10. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER
 METER AND BACKFLOW PREVENTION.
 11. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE CALLOUT
 DOMESTIC BACKFLOW PREVENTER AS RPPA AND FIRE BACKFLOW
 PREVENTER AS DCDA. SPECIFY LEAD FREE DESIGN ON ALL
 BACKFLOWS.
 12. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND
 NPDES NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE; AND
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION. IF THE ENGINEERING PLANS DO
 NOT INCLUDE AN EROSION CONTROL PLAN, THEN THE
 CONTRACTOR SHOULD SUBMIT ONE PRIOR TO RECEIVING THE
 ENGINEERING PERMIT.
 13. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES
 OF PROPOSED AND EXISTING WATER AND SEWER WITHIN RIGHT
 OF WAY AND SHOW ANY CROSSINGS/CONFLICTS.
 14. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 15. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD
 RIGHT OF WAY.
 16. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY
 ELEVATIONS AT MANHOLE TIE-IN.
 17. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY
 INFRASTRUCTURE IS PROPOSED IN ROW PLEASE SHOW ADJACENT
 SANITARY LATERAL LOCATIONS AND SHOW ADDRESSES OF
 ADJACENT PARCELS.
 18. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER
 INFRASTRUCTURE IS BEING REPLACED IN ROW, SHOW ADJACENT
 PARCEL ADDRESSES.
 19. FOR FORMAL ENGINEERING SUBMITTAL, WHEN TRENCHING IN
 IN CITY MAINTAINED ROADWAY AREAS ADD NOTE TO PROVIDE 50
 FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF
 PROPOSED TRENCH PER CURRENT CITY OF WPB STANDARD DETAIL
 GC-8.
 20. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-494-2262 OR
 [email protected]:
  
 -CALLOUT WIDTH OF SIDEWALK ON NORTH AND SOUTH SIDES OF
 PROPERTY ADJACENT TO 22ND ST AND 21ST ST.
  
 -SURVEY NOTE 1 SAYS THAT OFFICE HAS MADE NO SEARCH OF
 PUBLIC RECORDS. WHEN WILL THAT BE COMPLETED?
  
 -ADD WORDING ABOVE-GROUND TO LABEL OF 4 INCH WATER
 METER.
  
 -ADD LARGE ABOVE-GROUND METERED WATER SERVICE STANDARD
 DETAIL.
  
 -IS THERE A FDC CLEARANCE CONFLICT WITH DOMESTIC
 BACKFLOW ASSEMBLY?
  
 -LABEL PROPOSED MONUMENT AREA AND EXISTING UTILITY
 EASEMENTS ON CIVIL PLANS.
  
 -ON LANDSCAPING PLAN, ADD LEGEND IDENTIFYING THE
 DIFFERENT HATCHED AREAS.
  
 -LANDSCAPING PLAN DOES NOT SHOW UTILITIES. VERIFY NO
 CONFLICTS BETWEEN UTILITIES AND TREES. INCREASE
 CLEARANCE DISTANCE AND ADD ROOT BARRIERS AS NEEDED.
  
 -IF THERE SUFFICIENT CROSSING CLEARANCE DISTANCE
 BETWEEN 18 INCH RCP AND EITHER BACKFLOW ASSEMBLY
 PIPING?
  
 -FOOTPRINT OF PROPOSED WATER METER MAY BE LARGER THAN
 SHOWN.
  
 -ENSURE THAT ABOVE-GROUND WATER METER WILL NOT ENCROACH
 ON FIRE HYDRANT CLEARANCE AREA.
  
 -INCREASED PAVEMENT RESTORATION AREA NOT SHOWN FOR
 RELOCATED WATER SERVICE.
  
 -SHOW PROPOSED LOCATION OF RELOCATED METERED IRRIGATION
 WATER SERVICE AND BACKFLOW ASSEMBLY.
  
 -PARALLEL BACKFLOW ASSEMBLIES ARE RECOMMENDED ON
 DOMESTIC WATER SERVICE TO MINIMIZE WATER OUTAGES DUE TO
 BACKFLOW MAINTENANCE.
  
 -DID NOT SEE WATER SERVICE REMOVALS ON 22ND ST AND CUT
 AND CAP LABELS AS REQUESTED IN PUBLIC UTILITIES REVIEW
 COMMENT NUMBER 2 AND RESPONSE. ONE WATER SERVICE
 REMOVAL IS NOT SHOWN ON 21ST ST EITHER.
  
 QUESTIONS AND COORDINATION CONTACTS:
 O MARK HURLEY, FIELD CUSTOMER SERVICE SUPERVISOR WITH
 CITY OF WPB PUBLIC UTILITIES, REGARDING PLACEMENT OF
 BACKFLOW DEVICES AND WATER METERS. CONTACT HIM AT
 561-822-2262 OR [email protected]
 O RICK ROSSANO, SR. PROJECT COORDINATOR, ENGINEERING
 SERVICES DEPARTMENT AT 561-494-1098 [email protected]
 O MIKE TECHNOW, PROJECT ENGINEER, PUBLIC UTILITIES
 DEPARTMENT AT 561-494-1047 OR [email protected]
 O TRACY WARD, SR. STORMWATER ENGINEER, ENGINEERING
 SERVICES DEPT. AT 561-494-1120 OR [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved