Plan Review Notes
Plan Review Notes For Project Z21120018
Project Number Z21120018
Review Stop STORM
Sequence Number 3
Notes
Date Text
2022-08-01 14:58:09THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 7/19/2022 SUBMITTAL.
 1. [SATISFIED] REMOVE REFERENCES TO VOW (VILLAGE OF
 WELLINGTON) ON COVER.
  
 2. [SATISFIED] CONCEPTUAL ENGINEERING PLAN IS CONFUSING
 WITH EXISTING FEATURES SHOWN AND NOT SCREENED.
  
 3. [SATISFIED] RELOCATE DRAINAGE SYSTEM FROM UNDER
 STAIRS. ADDITIONAL COMMENT - OUTFALL PIPE IS UNDER THE
 SOUTH STAIRS OF BUILDING A. THIS PIPE IS WILL BE
 MAINTAINED BY THE PROPERTY OWNER. STAFF IS NOTIFYING
 ENGINEER TO SEE IF THE PIPE CAN BE INSTALLED IN ANOTHER
 LOCATION TO AVOID IMPACTING THE STAIRS IF THE PIPE
 NEEDS TO BE REPLACED/REPAIRED IN THE FUTURE.
  
 4. [SATISFIED] PROVIDE FLOW ARROWS SHOWING DIRECTION OF
 SURFACE RUNOFF. ADDITIONAL COMMENT - PROVIDE FLOW AREAS
 FOR THE AREAS AROUND THE BUILDING. PROPOSED SPOT GRADES
 ARE ONLY PROVIDED IN THE PARKING LOT.
  
 5. [PARTIALLY SATISFIED - SEE COMMENTS UNDER NEW
 COMMENTS BELOW] PROVIDE CROSS SECTIONS FROM:
 A. FACE OF BUILDING TO TAMARIND AVE CENTERLINE
 B. FACE OF BUILDING TO GRANT ST CENTERLINE
 C. FACE OF BUILDING TO 19TH ST CENTERLINE
 D. AT PROPOSED DRIVEWAY
 E. FROM EAST PROPERTY LINE TO FACE OF BUILDING ?A?
 F. FROM EAST PROPERTY LINE TO FACE OF BUILDING ?B?
  
 LABEL STREETS, PROPERTY LINES, SURFACE FEATURES AND
 GENERAL SURFACE SLOPES. PROVIDE DIMENSIONS FOR
 CURBS/CURB AND GUTTER, SIDEWALKS AND DISTANCE FROM
 PROPERTY LINE TO FACE OF BUILDING. INCLUDE PROPOSED
 PARALLEL PARKING AREAS.
  
 6. [SATISFIED] SHOW MILL AND RESURFACING LIMITS WITHIN
 THE STREETS.
  
 7. [SATISFIED] IDENTIFY ON THE CONCEPTUAL ENGINEERING
 PLAN WHERE THE SPECIAL TYPE F CURB AND GUTTER WILL BE
 CONSTRUCTED. REDRAW THE DETAIL IN ACAD AND PROVIDE
 ENGLISH UNITS. ADDITIONAL COMMENT - THE LOCATION FOR
 THIS CURB IS NOT CALLED OUT ON THE PGD PLAN.
  
 8. [SATISFIED] LABEL WHERE THE DRAINAGE CONTROL
 STRUCTURE WILL BE LOCATED AND PROVIDE A DETAIL OF THE
 STRUCTURE. NOTE THE CITY DOES NOT ALLOW THE USE OF
 BLEEDERS WITH EXFILTRATION TRENCHES.
  
 9. [NOT SATISFIED - NO NEW SIDEWALKS PER PREVIOUS
 RESPONSE] PROVIDE HATCHING PATTERNS FOR SIDEWALKS TO
 REMAIN AND FOR NEW/REPLACEMENT SIDEWALKS. ADDITIONAL
 COMMENT: SECTION A ON SHEET C3.2 CALLS OUT NEW SIDEWALK
 ALONG 19TH ST AND ALONG GRANT AVE. REVISE SECTION OR
 ADD PROPOSED SIDEWALK HATCH PATTERN ON SHEETS C2.1 AND
 C2.3 AND HATCH THE PROPOSED SIDEWALKS.
  
 10. [NOT SATISFIED] EXPLAIN HOW ACCESS FROM THE
 BUILDINGS TO THE PARKING LOT WILL BE PROVIDED FOR THE 4
 FT+/- GRADE DIFFERENTIAL. ADDITIONAL COMMENT (REVISED
 FOR 7/19 SUBMITTAL): PARKING LOT ELEVATION AT EAST END
 OF HANDICAP ACCESS AISLE IS APPROX.. 27.7 FT NAVD. THE
 LANDING AT THE BOTTOM OF 19.0 FT LONG RAMP IS AT
 ELEVATION 26.0 FT NAVD. RAMP SLOPE CALCULATES TO 8.9%,
 WHICH IS STEEPER THAN THE 1:12 ALLOWED FOR NEW
 CONSTRUCTION. THE SOUTH END OF THE 10 FT LONG RAMP IS
 47.5 FEET FROM THE NORTH CORNER OF THE BUILDING B. THE
 SOUTH SIDE OF THE DOOR FRAME OF THE APARTMENT ADJACENT
 TO THE RETAIL SPACE IS 47.08 FEET FROM THE NORTH CORNER
 OF BUILDING B SO THAT THE RAMP WILL BE IN FRONT OF THE
 DOOR.
  
 11. [SATISFIED] PER FIGURE XV-2: GENERAL PARKING
 DIMENSIONS IN SECTION 94-485 OF THE CITY'S CODE OF
 ORDINANCES, THE CURB LENGTH OF PARALLEL PARKING SPACES
 IS 22 FEET. THE SITE PLAN SHOWS 25 FEET AND GAPS IN THE
 PARKING SPACES ON TAMARIND AVE. ADDITIONAL COMMENT:
 SP-1 STILL SHOWS 25? DIMENSION AND DOES NOT DIMENSION
 THE NEW PARKING SPACE LAYOUT.
  
 12. [SATISFIED] CONSIDER ANGLING THE CURBING AT EACH
 END OF PROPOSED PARALLEL PARKING SPACES TO FACILITATE
 ACCESS TO AND FROM THE END SPACES.
  
 13. [SATISFIED] THE CITY?S OFFICIAL VERTICAL DATUM IS
 NGVD1929. THE CITY HAS ALLOWED THE USE OF NAVD1988 AS
 LONG AS THE CONVERSION EQUATION TO NGVD1929 AT THE
 PROJECT LOCATION IS PROVIDED. PROVIDE THE NAVD1988 TO
 NGVD1929 CONVERSION EQUATION ON THE SURVEY.
  
 14. [SAITISFIED - NO NEW CURBING IN THE RIGHT OF WAY]
 LABEL ANY NEW GUTTER OR CURB AND GUTTER IN THE RIGHT OF
 WAY.
  
 15. [SATISFIED] CONSIDER LOW IMPACT DEVELOPMENT
 DRAINAGE SYSTEMS IN LIEU OF EXFILTRATION TRENCHES.
  
 16. [SATISFIED] SHOW EXISTING GUTTER BETWEEN PLANTER AT
 NORTH END OF N. TAMARIND AVE AND THE CURB ALONG THE
 SIDEWALK.
  
 17. [SATISFIED - POLE WILL NEED TO BE SUPPORTED DURING
 PIPE INSTALLATION] STORM OUTFALL PIPE IS LESS THAN 2
 FEET FROM FPL CONCRETE POLE.
  
 18. [SATISFIED] INDICATE IF TRAFFIC CONTROL BOX IS TO
 REMAIN OR BE RELOCATED.
  
 19. [SATISFIED] UTILITY EASEMENT MAY BE NEEDED FOR THE
 EXISTING FIRE HYDRANT.
  
 20. [NOT SATISFIED] SHOW UTILITIES ON THE LANDSCAPE
 PLANS.
  
 21. [SATISFIED] EXFILTRATION TRENCH APPEARS TO CROSS
 THE EAST PROPERTY LINE AND ALSO BE IN CONFLICT WITH
 EXISTING RETAINING WALL. ADDITIONAL COMMENT: NOTE
 BOTTOM OF TRENCH WILL BE ABOUT 1 FOOT HORIZONTALLY FROM
 FACE OF WALL AND 5.5 FEET BELOW THE BOTTOM OF THE WALL.
  
 22. [SATISFIED ? RETAINING WALL IS PROPOSED.] 2.5 FT
 GRADE DIFFERENTIAL BETWEEN EAST PROPERTY LINE AND
 PARKING LOT.
  
 23. [SATISFIED] LABEL GRANT ST. CORRECTLY.
  
  
 NEW COMMENTS:
 24. [SATISFIED] ON SITE PLAN SHEETS AND ENGINEERING
 PLAN SHEETS UPDATE REFERENCES TO FDOT INDEX NUMBERS TO
 LATEST FDOT STANDARD PLAN NUMBERS.
  
 25.[SATISFIED] JUSTIFY 18-INCH DIAMETER PIPE SIZE FOR
 OUTFALL PIPE BETWEEN S-104 AND EXISTING CURB INLET.
  
 26. [NOT SATISFIED] SHOW ALL EXISTING PIPE CONNECTIONS
 (WITH PIPE SIZES) TO THE EXISTING CURB INLET AND THE
 STRUCTURES THESE PIPES ARE CONNECTED TO.
  
 27. [SATISFIED] PIPE BETWEEN S-102 AND S-103 CROSSES
 THE PROPERTY CORNER.
  
 28. [SATISFIED] SUGGEST MOVING THE MILL AND RESURFACING
 LIMITS ON GRANT AVE TO THE EAST SIDE OF THE STAMPED
 ASPHALT CROSS WALK.
  
 29. [SATISFIED] PROPOSED SPOT GRADE OF 28.2 FT NAVD AT
 EAST SIDE OF PROPOSED DRIVEWAY TO 19TH STREET IS LOWER
 THAN THE EXISTING SPOT GRADE OF 29.13 FT NAVD. SHOW HOW
 THE ROAD WILL TRANSITION TO THE PROPOSED GRADE.
  
 30. - 33 [NOT SATISFIED ? NOTE PREVIOUS SECTIONS WERE
 REPLACED WITH NEW SECTIONS ON THE 7/19 SUBMITTAL. THE
 COMMENTS BELOW ARE FOR THE NEW SECTIONS.
  
 30. SECTION A (SHEET C3.2):
 A. SECTION APPEARS TO CORRESPOND TO SECTION B SYMBOL ON
 SHEET C2.1.
 B. CHANGE LABEL OF GRANT AVE TO GRANT ST.
 C. SIDEWALKS ON GRANT ST AND 19TH ST APPEAR TO HAVE
 THICKENED EDGE AT BACK OF SIDEWALK. PROVIDE A DETAIL
 FOR THE SIDEWALK.
 D. DOOR AND WINDOW LAYOUT FOR BUILDINGS A AND B DO NOT
 MATCH THE ARCHITECTURAL ELEVATION DRAWINGS.
 E. CONFIRM THE GRADES PROVIDED FOR GRANT ST. THE EP IS
 SHOWN HIGHER THAN THE CENTERLINE.
  
 31. SECTION B (SHEET C3.2):
 A. SECTION APPEARS TO CORRESPOND TO SECTION A SYMBOL ON
 SHEET C2.1.
 B. VERIFY ELEVATION FOR EAST SIDE OF DRIVE AISLE
 (29.7).
 C. SIDEWALK ALONG TAMARIND AVE APPEARS TO HAVE A
 THICKENED EDGE.
 D. CENTER OF DRIVE AISLE APPEARS TO BE LOW SPOT
 (INVERTED CROWN) BUT THE DRAINAGE STRUCTURES ON SHEET
 C2.1 ARE 14+ FEET FROM THE EAST EDGE OF THE PARKING
 LOT.
  
 32. SECTION C (SHEET C3.2):
 A. THIS SECTION DOESN?T APPEAR TO BE FOR THIS
 DEVELOPMENT. BUILDING A WIDTH IS CALLED OUT AS 132 FEET
 WHEREAS IN SECTION A THE BUILDING A WIDTH IS 88 FEET.
 B. PROVIDE A SECTION CORRESPONDING TO THE SECTION C
 SYMBOL ON SHEET C2.1.
  
 36. [NOT SATISFIED] ARCHITECTURAL NORTH AND SOUTH
 ELEVATIONS APPEAR TO BE MISLABELED ON SHEETS
 A-2.1/A2.2B AND SHEETS A-2.1A/A-2.2A.
  
 NEW COMMENTS ON 7/19/22 SUBMITTAL:
  
 37. PROVIDE A CROSS SECTION FROM THE CENTER OF THE
 PARKING LOT TO THE EAST FACE OF BUILDING, CENTERED ON
 THE RAMP FROM THE PARKING LOT TO THE FIRST FLOOR
 SIDEWALK. PROVIDE HORIZONTAL DIMENSIONS AND ELEVATIONS
 AT EACH GRADE BREAK.
  
 38. LABEL BUILDING A AND BUILDING B ON THE CIVIL
 DRAWINGS.
  
 39. LABEL THE EXISTING UTILITIES (PIPE SIZE AND
 MATERIAL) IN THE RIGHTS OF WAYS.
  
 40. HOW DOES ONE ACCESS BUILDING A FROM THE PARKING
 LOT? THERE DOESN?T APPEAR TO BE A SIDEWALK CONNECTION
 BETWEEN THE TWO BUILDINGS ON THE EAST SIDE OF THE
 BUILDINGS.
  
 41. CALLOUT THE FDOT CURB RAMP STYLE FOR THE MIDBLOCK
 CROSS WALK ON BOTH SIDES OF TAMARIND AVE.
  
 42. PROVIDE PROPOSED INVERT ELEVATION FOR PIPE
 CONNECTION TO EXISTING INLET. PROVIDE THE BOTTOM
 ELEVATION INVERT ELEVATION FOR THE EXISTING PIPE(S)
 CONNECTED TO THE INLET.
  
 43. SOUTH STAIRWELL OF BUILDING B APPEARS TO CONFLICT
 WITH THE WEST RETAINING WALL OF THE PARKING LOT.
  
 44. PROVIDE A YARD DRAIN AT WEST END OF THE AREA
 BETWEEN THE TWO BUILDINGS TO COLLECT RUNOFF BEFORE IT
 FLOWS OVER THE SIDEWALK.
  
 45. SLOPE OF PARKING LOT BETWEEN S-101 AND BACK OF
 SIDEWALK APPEARS TO BE CLOSE TO 9%.
  
 46. SHOW CURBING ALONG SOUTH AND EAST SIDES OF PARKING
 LOT ON THE CIVIL DRAWINGS. SHEET C2.3 CALLS OUT TYPE D
 CURB.
  
 46. BIKE LANE STRIPING SHALL FOLLOW THE CITY STANDARD
 DETAILS AND THE MUTCD.
  
 47. SIGNAGE AND STRIPING NEEDED FOR THE MID-BLOCK CROSS
 WALK.
  
 48. REVIEW PIPE SIZES AND INVERT ELEVATIONS LISTED ON
 THE CONTROL STRUCTURE S-104 DETAILS.
  
 49. REVIEW PIPE MATERIAL LISTED ON THE CONTROL
 STRUCTURE S-102 DETAILS.
  
 50. MOVE CONSTRUCTION ACCESS AREA OUTSIDE OF THE ROAD
 RIGHT OF WAY.
  
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)