Plan Review Notes
Plan Review Notes For Project Z21080015
Project Number Z21080015
Review Stop STORM
Sequence Number 2
Notes
Date Text
2022-04-14 12:02:10THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
  
 1. LABEL ALL THE STREETS ON ALL OF THE SHEETS. FOR
 EXAMPLE, SHEET C1.01 ONLY LABELS PINEWOOD AVE. NONE OF
 THE EAST-WEST STREETS ARE LABELED.
  
 2. COMPLETE THE PAVING, GRADING AND DRAINAGE NOTES ON
 THE PGD PLAN SHEETS. SOME OF THE NOTES DO NOT AGREE
 WITH THE VERTICAL DATUM LABEL AT THE BOTTOM OF THE
 SHEETS.
  
 3. EXFILTRATION TRENCH FOR TREATING RUNOFF FROM ONSITE
 AREAS SHALL NOT BE LOCATED WITHIN THE RIGHT OF WAY.
  
 4. ON SHEET C2.03 THERE IS A NEW DRAINAGE STRUCTURE ON
 THE EAST SIDE OF PINEWOOD AVE ABOUT 40 FEET NORTH OF
 THE CENTERLINE OF NORTHWOOD ROAD. THIS INLET IS SHOWN
 NEXT TO AN EXISTING INLET THAT IS BEING CONVERTED TO A
 VALLEY GUTTER INLET. IS THE NEW INLET NEEDED?
  
 5. WHAT WILL BE THE MAXIMUM CROSS SLOPE OF THE
 ON-STREET PARKING SPACES?
  
 6. LABEL THE PARKING AREAS ON THE CROSS SECTIONS.
  
 7. ADVISE IF THE WEST DROP CURB ON PINEWOOD AVE WILL BE
 PARALLEL TO THE WEST RIGHT OF WAY. THE 9.0 FT DIMENSION
 ON SECTION B-B DOES NOT APPEAR TO REACH THE 2 FEET DROP
 CURB.
  
 8. SIDEWALK CROSS SLOPES SHALL NOT EXCEED 2 PERCENT.
  
 9. THE DIMENSIONS FOR THE PARKING AREAS ON SECTION D-D
 AND SECTION E-E (FOR BROADWAY AVE) APPEAR TO INCLUDE
 THE TYPE 'D' CURB.
  
 10. EXTEND SECTION F-F TO THE PARKING LOT ON THE WEST
 SIDE OF PINEWOOD AVE. DIMENSION THE SIDEWALKS, CURB AND
 GUTTER, TRAVEL LANES AND PARKING AREA.
  
 11. DIMENSION MINIMUM BUILDING SETBACKS ON THE CROSS
 SECTIONS.
  
 12. PROVIDE CROSS SECTION OF BROADWAY AVE SOUTH OF
 NORTHWOOD ROAD. EXTEND SECTION FROM FACE OF BUILDING TO
 FACE OF BUILDING. DIMENSION SIDEWALKS, CURB AND GUTTER,
 PARKING AREAS, TRAVEL LANES, SETBACKS FROM R/W, ETC.
  
 13. REVISE THE PARKING SPACE STRIPING DETAIL TO MATCH
 CITY CODE.
  
 14. THE CITY DOES NOT ALLOW THE USE OF BLEEDERS WITH
 EXFILTRATION TRENCHES.
  
 15. LABEL RIGHT OF WAYS PROPOSED TO BE ABANDONED ON THE
 PLAN SHEETS.
  
 16. RCP PIPE (MINIMUM 15 INCHES IN DIAMETER) TO BE
 INSTALLED WITHIN THE RIGHT OF WAY.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA. STORMWATER CALCULATIONS WILL BE REVIEWED WITH
 THE ENGINEERING PERMIT SUBMITTAL.
  
 2. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION, IF REQUIRED.
  
 3. PROVIDE AN EROSION CONTROL PLAN WITH DETAILS.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)