Plan Review Notes
Plan Review Notes For Project Z21080015
Project Number Z21080015
Review Stop ENG - PPRC
Sequence Number 2
Notes
Date Text
2022-04-09 14:19:23Z21080015, 0017 - NORTHWOOD SQUARE, AND ABANDONMENTS
 3.30.22 SUBMITTAL
  
 PLEASE PROVIDE RESPONSES TO MY COMMENTS FROM NOV 2021
 SUBMITTAL:
  
 COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR, ENG.
 SERVICES DEPT., 561-494-1098 [email protected] :
  
 GENERAL:
 O PLEASE RESPOND TO ALL COMMENTS IN WRITING, AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
 O THE CITY OF WEST PALM BEACH HAS A NUMBER OF
 REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY
 AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND
 WASTEWATER UTILITIES WITHIN THE CITY. PLEASE SEE
 DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AT THE LINK
 BELOW:
 A. HTTP://WPB.ORG/CMSPAGES/GETAMAZONFILE.ASPX?PATH=~\WP
 B_WEBSITE\MEDIA\ENGINEERING\DEVELOPMENT-APPLICATION-FUL
 L-PACKAGE_2016.PDF&HASH=7BD4DD7EB6115181D8C5977BCC02A97
 B1960045731D3658206F27451722716EF
 B. THIS AND OTHER RELATED ENGINEERING DOCUMENTS CAN BE
 FOUND HERE:
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
 C. ALSO SEE: CODE OF ORDINANCES, CITY OF WEST PALM
 BEACH, FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08,
 ADOPTED SEPT. 22, 2008. (SUPPLEMENT NO. 18)
 CHAPTER 90 UTILITIES, ARTICLE I. IN GENERAL,
 SEC. 90-7. POLICY REGARDING EXTENSION OF WATER OR SEWER
 SERVICE FACILITIES OF THE CITY.
 THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE
 CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY
 BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS,
 BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION.
 O AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, REFER TO THE LINK BELOW:
 A. HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PU
 BLICATIONS/BACKFLOW-CROSS-CONNECTION- CONTROL-MANUAL
 O PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1079 FOR FURTHER
 ASSISTANCE. NOTE THAT FIELD RECORDS ARE FOR INFORMATION
 ONLY. FIELD VERIFY UTILITY LOCATIONS USING FIELD
 SURVEY, POT-HOLING, SOFT DIGS ETC.
  
 BACKFLOW ASSEMBLY AND METERS:
  
 O SHOW AND LABEL ANY EXISTING OR PROPOSED WATER
 SERVICES AND WATER METERS FOR THE PARKING LOTS, ALONG
 WITH WHAT IS HAPPENING TO THEM.
 O SHOW EXISTING AND PROPOSED DEDICATED UTILITY
 EASEMENTS TO ALLOW ACCESS FOR CITY PERSONNEL TO
 PROPOSED UTILITY WATER METERS. VERIFY THAT THERE ARE NO
 STRUCTURES WITHIN EASEMENT.
 O PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED LOCATION
 OF WATER METER AND BACKFLOW
 PREVENTION.
 O BACKFLOWS SHALL BE INSTALLED ON PRIVATE PROPERTY
 OUTSIDE OF EASEMENTS AND RIGHTS OF WAY. DOMESTIC WATER
 METERS SHALL BE INSTALLED IMMEDIATELY ADJACENT TO
 PROPERTY LINE. 3 INCH AND LARGER WATER METERS SHALL BE
 INSTALLED ABOVE-GROUND ONLY.
 O CALLOUT DOMESTIC BACKFLOW PREVENTER AS RPPA (MAKE
 NOTE USC APPROVED) AND FIRE BACKFLOW PREVENTER AS DCDA.
  
 WATER/WASTEWATER PLAN:
 O PROVIDE VERTICAL DATUM AND DATUM CONVERSION
 INFORMATION (NAVD 1988 AND NGVD 1929).
 O SHOW PROJECT ADDRESS ON ALL PLAN SHEETS.
 O PROVIDE LEGEND ON ALL PLAN SHEETS TO INCLUDE
 STREETLIGHT, SIGN POSTS, TRANSFORMER BOXES ETC.
 O PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, INCLUDING STUBS TO EACH
 PROPERTY LINE FOR WATER AND SANITARY SEWERS, THE MAKE
 AND MODEL OF ALL VALVES, POTABLE AND IRRIGATION METERS,
 BACKFLOWS, FIRE HYDRANTS AND FDCS, AND OTHER DEVICES TO
 BE INSTALLED ON THE SYSTEM, CATCH BASINS, CULVERTS,
 DITCHES INCLUDING GRADES, PIPES SIZES, MATERIALS,
 ELEVATIONS, ASSUMPTIONS, CALCULATIONS, INVERT
 ELEVATIONS FOR ALL INLETS AND MANHOLES AND PROFILES OF
 SANITARY SEWER LINES.
 O GATE VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR
 SIDEWALK. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW.
 O DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN
 VIEW FOR ALL SANITARY AND STORM SEWERS.
 O SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL.
 O PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES LOCATED ON THE RIGHT-OF-WAY.
 O PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES PER CITY OF WEST PALM BEACH STANDARD
 DETAIL GN-2 SERIES, AT ALL UTILITY CROSSINGS.
 O SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE DIRECTLY
 TO ENGINEERING (SHEET 33 OF CITY OF WPB DEVELOPMENT
 APPLICATION). PROVIDE CALCULATIONS ON PLANS OF EXISTING
 AND PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE,
 MAXIMUM AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS
 SHALL BE PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008
 FOR WATER.
 O PROVIDE FIRE FLOW TEST DATA.
 O PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND
 STORMWATER INFRASTRUCTURE ALONG ENTIRE PROJECT
 FRONTAGE.
 O CUT AND CAP UTILITIES NOT IN USE AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 ROW.
 O WHEN PROPOSED, WATER MAINS IN CITY RIGHT OF WAY SHALL
 BE MADE OF DUCTILE IRON PIPE (NOT PVC) AND SPECIFY
 PROPOSED LENGTH IN FEET.
 O CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 O PROVIDE CLEANOUTS FOR PROPOSED SANITARY LINE ONSITE
 JUST INSIDE PROPERTY LINE, AT JOINTS AND EVERY 75 FEET.
 O ADD NOTE TO PLANS SPECIFYING CITY?S DOWNSTREAM LIFT
 STATION NUMBER.
 O PROVIDE ONSITE CLEANOUTS NEAR PROPERTY LINE FOR
 PROPOSED SANITARY LATERALS.
 O LABEL WATER LINES AS PRIVATE WHERE APPLICABLE.
 O PLEASE SHOW AND LABEL EXISTING AND PROPOSED GREASE
 TRAPS (IF ANY).
 O PER CITY STANDARDS MAINTAIN MINIMUM DISTANCE BETWEEN
 OUTSIDE DIAMETER OF CITY PIPE AND ROOT BARRIER.
  
 FORMAL ENGINEERING REVIEW:
 O FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND NPDES
 NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE;
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION.
 O FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 EASEMENT FOR PLACEMENT OF PROPOSED WATER METERS.
 O FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES OF
 WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS.
 O FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 O FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES
 ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY
 LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT
 PARCELS.
 O FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES ARE
 BEING REPLACED IN ROW, SHOW ADJACENT PARCEL ADDRESSES.
 O FOR FORMAL ENGINEERING SUBMITTAL, ADD NOTE TO PROVIDE
 50 FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF
 PROPOSED TRENCH IN CITY MAINTAINED ROADWAY AREAS PER
 CITY OF WPB STANDARD DETAIL GC-8.
 O FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 CALCULATIONS OF PERVIOUS AND IMPERVIOUS AREAS FOR
 PROPOSED IMPROVED AREAS.
  
 MARK HURLEY, FIELD CUSTOMER SERVICE SUPERVISOR WITH
 CITY OF WPB PUBLIC UTILITIES, 561-494-2262 OR
 [email protected] :
  
 -PINEWOOD AVE VACATION LEGAL DESCRIPTION STATES THAT
 THE LANDS ARE IN MONROE COUNTY FLORIDA. PLEASE VERIFY
 IT IS WORDED CORRECTLY OR UPDATE.
  
 -A0.02 SAYS 360 UNITS, BUT LOS ANALYSIS SAYS 370 UNITS.
 PLEASE VERIFY BOTH AND UPDATE AS NEEDED.
  
 -SHOW AND LABEL PROPOSED AND EXISTING SIDEWALK
 EASEMENTS ON CIVIL PLANS. SOME ADDITIONAL MAY BE
 REQUIRED.
  
 -ARE THERE ANY OUTSIDE ADA PARKING SPOTS? IF NOT, ARE
 ANY NEEDED OR REQUIRED?
  
 -A301 SHOWS GREENSPACE ISLANDS IN SOUTHWEST OUTSIDE
 PARKING LOT BUT PGD PLAN DOES NOT. PLEASE MAKE SURE ALL
 PLANS MATCH GENERAL DESIGN LAYOUT.
  
 -A301 HAS SOME HATCHED 20FT BY 20FT TRIANGLES. PLEASE
 IDENTIFY THEM IN LEGEND. IF THEY ARE SIGHT TRIANGLES,
 IS IT ALRIGHT FOR THE TREES TO BE IN THEM?
  
 -ON A402 AND A403 PLEASE CALLOUT DIMENSIONS OF PARKING
 GARAGE ENTRANCE.
  
 -ON A404 PLEASE CALLOUT DIMENSIONS OF BROADWAY AVE
 TUNNELS
  
 -CIVIL PLANS NOT SIGNED, SEALED, AND DATED.
  
 -ON C1.04 BETWEEN 550 AND 540 NORTHWOOD, DEMO PLAN SAYS
 PARTY WALL. IF THAT IS A SHARED WALL, PLEASE HIGHLIGHT
 BETTER AND ALSO INDICATE IF WALL WILL REMAIN OR BE
 REPLACED.
  
 -ON C3.01 IS THE INTENT FOR THE PROPOSED 8 INCH PVC
 WATER MAIN TO BE PRIVATELY OWNED AND MAINTAINED OR CITY
 OWNED AND MAINTAINED?
  
 -CITY OWNED WATER MAINS AND WATER SERVICES LARGER THAN
 2 INCHES SHOULD BE DIP.
  
 -CALLOUT BACKFLOW ASSEMBLIES AND WATER METERS. ADD SIZE
 TO LABEL.
  
 -C3.01 SOUTHWEST BUILDING A FIRE AND WATER SERVICE
 LABELS APPEAR TO BE REVERSED. FIRELINE BACKFLOW
 ASSEMBLY ALSO LOOKS CLOSE TO PARKING SPOT TRAFFIC. MAY
 NEED INCREASE DISTANCE TO PREVENT DAMAGE.
  
 -WATER SERVICE LABELS ARE AMBIGUOUS AS TO WHICH
 PORTIONS ARE PRIVATE. ALSO UNCLEAR AS TO SIZING WHEN
 SAYING 3 INCH BUT THE TAP IS FOUR INCHES AND REQUIRED
 PIPING WOULD BE AT LEAST 4 INCHES.
  
 -FOR ANY PROPOSED WATER METERS LARGER THAN 2 INCHES,
 ADD WORDING ABOVE GROUND TO LABELS.
  
 -C3.01: ADD SMALL CIRCULAR OBJECTS IN SIDEWALK TO
 LEGEND AND IDENTIFY THEM.
  
 -ENSURE ARCHITECTURAL PLANS COMPLY WITH NOTE 21 ON
 UTILITY PLAN REGARDING VERTICAL CLEARANCE DISTANCES.
  
 -NOTE 20 ON UTILITY PLAN DOES NOT SEEM TO MAKE SENSE. A
 DDCV IS A TYPE OF BACKFLOW PREVENTER.
  
 -NOTE 14 ON UTILITY PLAN: VERIFY IF THERE WILL BE ANY
 COUNTY UTILITIES IN PROJECT AREA. IF NOT, THEN REVISE
 OR REMOVE.
  
 -FIRELINE BACKFLOW ASSEMBLY LOCATIONS WOULD ONLY BE
 ACCEPTABLE IF ROW IS ABANDONED AND AREA IS PRIVATELY
 OWNED.
  
 -BACKFLOW ASSEMBLIES FOR DOMESTIC METERED WATER
 SERVICES APPEAR TO BE MISSING. THEY SHOULD BE OUTSIDE
 OF BUILDING, ADJACENT PROPERTY LINE, ON PRIVATE
 PROPERTY, WITH DISTANCE MINIMIZED TO METER, BUT NOT
 LOCATED IN SIDEWALK PEDESTRIAN TRAFFIC. CLEARLY SHOW
 AND LABEL THEM.
  
 -FOR FIRELINE BACKFLOW ASSEMBLY AT NORTHEAST BUILDING
 OFF BROADWAY, ATTEMPT TO RELOCATE SLIGHTLY NORTH TO
 REDUCE PIPE DISTANCE. IF CANNOT EXPLAIN CONFLICT.
  
 -C3.02: FDC NEEDS TO BE ON PRIVATE PROPERTY AND OUT OF
 PEDESTRIAN TRAFFIC AS WELL AS NOT IMPEDING VEHICLE
 DOORS. IT MUST ALSO BE CLEARLY VISIBLE AND TYPICALLY
 REQUIRES SIGNAGE.
  
 -C3.02: FIRELINE BACKFLOW ASSEMBLY LOOKS TO CONFLICT
 WITH CURB OR GUTTER AND IS CLOSE TO VEHICLES.
  
 -C3.03: PROPOSED 24 INCH WATER MAIN SHOULD BE DIP
 INSTEAD OF PVC; ADD 24 INCH VALVES AT 24 INCH TEES IN
 OFFSET DIRECTIONS;
  
 -ADD NOTE ON UTILITY PLAN SHEETS THAT LINESTOPS OR
 INSERTION VALVES MAY BE REQUIRED AS DIRECTED BY CITY OF
 WEST PALM BEACH UTILITIES OR ENGINEER OF RECORD TO
 MINIMIZE WATER OUTAGES.
  
 -THERE ARE SOME DOORS THAT OPEN TO PLAZA CLOSE TO A
 LANDSCAPING AREA THAT WOULD SEEM TO BLOCK PEDESTRIAN
 MOVEMENT. IS THAT ALRIGHT?
  
 -BUILDING B EAST FIRELINE LABELED 6 BY 4, BUT SHOULD BE
 8 BY 4; ALSO SHOW AND LABEL DOMESTIC BACKFLOW ASSEMBLY;
 UTILITY EASEMENT FOR METER NOT SHOWN AND LABELED.
  
 -VERIFY BUILDING B WEST FDC LOCATION IS ACCEPTABLE WITH
 WPB PLANNING. ALSO VERIFY BUILDING C SOUTH FDC LOCATION
 WITH THEM.
  
 -BUILDING C 4 INCH WATER MAIN DOES NOT DEADEND PER WPB
 GIS. PLEASE VERIFY AND UPDATE UTILITY PLAN AS NEEDED.
  
 -BUILDING CS CANNOT HAVE BACKFLOW ASSEMBLIES IN RIGHT
 OF WAY. NEEDS TO BE ON PRIVATE PROPERTY.
  
 -DID NOT SEE FIRELINES WITH DCDAS FOR BUILDING CS.
 VERIFY THEY ARE NOT NEEDED OR REQUIRED FOR THESE
 BUILDINGS OVER 2 STORIES.
  
 -ARE ANY WERE LATERALS MISSING FOR BUILDINGS ON WEST
 SIDE OF BROADWAY?
  
 -APPLICANT MUST FOLLOW ALL RULES REGARDING SUBMETERING
 AND REMETERING
  
 -THERE ARE SPECIAL REQUIREMENTS AND RESTRICTIONS
 REGARDING PLUMBING CROSSING RIGHT OF WAYS AND STREETS.
  
 -NOTE 16 MENTIONED A LIFT STATION. ARE THERE ANY
 PROPOSED LIFT STATIONS FOR THIS PROJECT?
  
 -VERIFY ALL REQUIRED PAVEMENT RESTORATION FROM UTILITY
 WORK IS SHOWN. LOOKS LIKE THERE IS AT LEAST SOME
 MISSING ON 25TH ST.
  