| 2021-08-12 09:24:42 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY'S OFFICIAL VERTICAL DATUM PER CITY CODE IS |
| | NGVD1929. THE CITY IS ALLOWING SURVEYS AND PLANS TO USE |
| | NAVD1988 PROVIDED THE CONVERSION EQUATION BETWEEN |
| | NAVD1988 AND NGVD1929 IS ALSO PROVIDED. PROVIDE THE |
| | CONVERSION EQUATION TO NGVD1929 ON THE SURVEY. |
| | |
| | 2. PROVIDE PIPE MATERIAL, PIPE INVERTS OF EXISTING |
| | DRAINAGE SYSTEM IN THE PUBLIC RIGHTS OF WAY. |
| | |
| | 3. THE STORM PIPE ALONG THE WEST PROPERTY LINE APPEARS |
| | TO BE LOCATED UNDER THE PROPOSED BUILDING. |
| | |
| | 4. DO NOT CONNECT THE ONSITE DRAINAGE SYSTEM FOR 300 |
| | BANYAN TO THE EXISTING ALLEY DRAINAGE SYSTEM. |
| | |
| | 5. EXPLORE CONNECTING THE ROOF DRAINS IN THE ALLEY FOR |
| | 301 CLEMATIS TO THE ALLEY DRAINAGE SYSTEM. |
| | |
| | 6. INDICATE IF THE EXISTING ELECTRICAL CONDUITS WILL |
| | REMAIN ONSITE. |
| | |
| | 7. MOVE SANITARY MH2 OUT OF THE ALLEY R/W. |
| | |
| | 8. ON THE EROSION CONTROL PLAN, SHOW INLET PROTECTION |
| | FOR DRAINAGE STRUCTURES WITH THE R/W. |
| | |
| | 9. PROVIDE DETAIL FOR SPECIAL TYPE 'F' CURB AND GUTTER |
| | USED IN THE DOWNTOWN AREA. |
| | |
| | 10. PROVIDE TYPICAL CROSS SECTIONS FROM THE FACE OF |
| | BUILDING TO THE CENTERLINE OF THE R/W. |
| | |
| | 11. PROVIDE CROSS SECTION OF THE ALLEY FROM BUILDING |
| | FACE TO BUILDING FACE. |
| | |
| | 12. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP |
| | CRITERIA. |
| | |
| | 13. THE CITY DOES NOT ALLOW THE USE OF BLEEDERS IN |
| | CONTROL STRUCTURES USED TO SURCHARGE EXFILTRATION |
| | TRENCHES. |
| | |
| | 14. CONSIDER ALTERNATIVE STORMWATER STORAGE SYSTEM. |
| | EXFILTRATION SYSTEMS CAN HAVE A SHORT LIFE SPAN. |
| | |
| | 15. COORDINATE DESIGN WITH THE BANYAN BLVD STREETSCAPE |
| | PROJECT. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE COPY OF SFWMD ERP PERMIT(S) BEFORE START OF |
| | CONSTRUCTION. |
| | |
| | 4. PROVIDE A COPY OF THE DRAINAGE CALCULATIONS WITH THE |
| | ENGINEERING PERMIT APPLICATION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |