Plan Review Notes
Plan Review Notes For Project Z21070016
Project Number Z21070016
Review Stop ENG - PPRC
Sequence Number 2
Notes
Date Text
2021-09-29 17:28:10COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR, ENG.
 SERVICES DEPT., 561-494-1098 [email protected] :
  
 1. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 2. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER.
 3. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND
 STORMWATER PIPES ALONG ENTIRE PROJECT FRONTAGE. CCTV IS
 A CONDITION OF SITE PLAN APPROVAL.
 4. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED AREAS
 ON PAVING PLANS.
 5. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 6. FOR FORMAL ENGINEERING SUBMITTAL , PLANS SHALL SHOW
 PROPOSED LOCATIONS AND DIMENSIONS OF ALL WATER,
 STORMWATER, AND SANITARY AND SEWER LINES, INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, METERS, AND
 OTHERS DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. ALL
 AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE VIEW.
 DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN
 VIEW FOR ALL SANITARY AND STORM SEWERS. ADDITIONALLY,
 PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES LOCATED ON THE RIGHT-OF-WAY.
 7. FOR FORMAL ENGINEERING SUBMITTAL , CUT AND CAP
 UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY
 LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY.
 8. FOR FORMAL ENGINEERING SUBMITTAL , PROVIDE DEDICATED
 UTILITY EASEMENTS TO ALLOW ACCESS FOR CITY PERSONNEL TO
 PROPOSED UTILITY WATER METERS.
 9. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER
 METER AND BACKFLOW PREVENTION.
 10. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE CALLOUT
 DOMESTIC BACKFLOW PREVENTER AS RPPA AND FIRE BACKFLOW
 PREVENTER AS DCDA. SPECIFY LEAD FREE DESIGN ON ALL
 BACKFLOWS.
 11. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND
 NPDES NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE; AND
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION. IF THE ENGINEERING PLANS DO
 NOT INCLUDE AN EROSION CONTROL PLAN, THEN THE
 CONTRACTOR SHOULD SUBMIT ONE PRIOR TO RECEIVING THE
 ENGINEERING PERMIT.
 12. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES
 OF PROPOSED AND EXISTING WATER AND SEWER WITHIN RIGHT
 OF WAY AND SHOW ANY CROSSINGS/CONFLICTS.
 13. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 14. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD
 RIGHT OF WAY.
 15. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY
 ELEVATIONS AT MANHOLE TIE-IN.
 16. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES
 ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY
 LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT
 PARCELS.
 17. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES
 ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL
 ADDRESSES.
 18. FOR FORMAL ENGINEERING SUBMITTAL, WHEN TRENCHING IN
 IN CITY MAINTAINED ROADWAY AREAS ADD NOTE TO PROVIDE 50
 FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF
 PROPOSED TRENCH PER CURRENT CITY OF WPB STANDARD DETAIL
 GC-8.
 19. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-494-2262 OR
 [email protected]:
  
 1. VERIFY WITH WPB FIRE MARSHAL THAT PROPOSED DCDA
 LOCATION IS ACCEPTABLE.
 RESPONSE: WE HAVE COORDINATED WITH MARK HURLEY TO
 DETERMINE THE PROPER LOCATION FOR DCDA.
 NOT SATISFIED. CANNOT RECALL COORDINATING WITH
 APPLICANT ON DCDA LOCATION AND NO VERIFICATION FROM WPB
 FIRE MARSHAL. PLEASE ALSO REFERENCE REVIEW COMMENTS AND
 RESPONSES FROM FIRE MARSHAL 7C AND ANA MARIA 19.
  
 12. WILL ALL OF THE METERED PARKING SPOTS ON DATURA
 REMAIN AFTER PROJECT COMPLETED?
 RESPONSE: A PORTION OF THE METERED PARKING WILL BE
 REMOVED DUE TO REDESIGN OF DATURA STREET LAYOUT.
 EMAIL SEAN SAMUELS [email protected] AND COPY DANIEL
 GIUST [email protected] AND ANA MARIA APONTE
 [email protected] REGARDING THIS ISSUE.
  
 20. LANDSCAPING PLAN ONLY SHOWS TREES BEING REMOVED.
 PLEASE UPDATE LANDSCAPING PLAN TO SHOW ANY OTHER
 PROPOSED OR EXISTING LANDSCAPING SUCH AS TREES, BUSHES,
 PLANTS, AND GRASS. VERIFY TREES WILL NOT CONFLICT WITH
 UTILITIES. ALSO ADD SEPARATE SHEET SHOWING UTILITIES
 OVERLAID WITH LANDSCAPING.
 RESPONSE: NOT A CIVIL COMMENT, HAVE LANDSCAPE RESPOND.
 NOT SATISIFIED. DID NOT SEE LANDSCAPING PLAN WITH
 PROPOSED LANDSCAPING IN RESUBMITTAL PACKAGE.
  
 NEW COMMENTS:
  
 -CIVIL, SITE, AND LANDSCAPING PLANS DO NOT APPEAR TO
 MATCH EACH OTHER WITH RESPECT TO THE WATER SERVICES AND
 BACKFLOW ASSEMBLIES. SITE PLANS ONLY SHOW BACKFLOW
 ASSEMBLIES, BUT SHOW THEM IN THE NORTHWEST AREA OF
 PROPERTY CONTRARY TO THE OTHER PLAN SETS. PLEASE MAKE
 SURE ALL PLANS MATCH, AND ALSO SHOW THE LARGE ABOVE
 GROUND METER ON THE SITE PLANS.
  
 -UTILITY EASEMENT IS NOT NEEDED IN THE RIGHT OF WAY.
  
 -RELOCATE IRRIGATION METER ADJACENT THE PROPERTY LINE.
  
 -ADD UTILITY EASEMENT FOR IRRIGATION METER AND UPSTREAM
 PIPING IF SOUTH OF PROPERTY LINE.
  
 -BACKFLOW ASSEMBLIES MAY NOT BE IN UTILITY EASEMENTS.
 MAY NEED TO MAKE SEPARATE SYMBOL OR ICON FOR THE
 BACKFLOW ASSEMBLIES TO DISTINGUISH THAT.
  
 -LABEL IRRIGATION BACKFLOW ASSEMBLY AS RP TYPE.
  
 -SEWER LATERAL CONNECTION AT SEWER MAIN IS CLOSE TO
 FIBER OPTIC BOX AND MAY NEED TO BE RELOCATED UPON
 FURTHER REVIEW AT ENGINEERING SUBMITTAL.
  
 -UTILITY PLAN SHOWS EXISTING POLE CONFLICT WITH
 PROPOSED ALLEY BAY DRIVE ENTRANCE.
  
  
 COMMENTS FROM MICHAEL TECHNOW, PROJECT ENGINEER, WPB
 PUBLIC UTILITIES, 561-494-1047, [email protected] :
 -ADD LOS TO PLAN SHEET.
 -PROVIDE NAVD CONVERSION.
 -PLEASE ADD NOTE THAT THIS IS WITHIN LS 21 SERVICE
 AREA.
 -PLEASE SHOW ALL VALVES, SHOW PIPE TYPE AND SIZE.
 -SHOW DIRECTION OF FLOW.
 -CALL OUT SIZE OF METER.
 -WHAT IS UGU? PLEASE SHOW ON LEGEND.
 -PROVIDE POST CCTV OF SERVICE LATERALS.
 -NOTE TO CUT AND CAP UNUSED SERVICES AT THE MAIN.
 -CALL OUT SIZE/MATERIAL OF GAS MAIN.
 -CALL OUT SIZE/MATERIAL OF SERVICE.
 -WHAT SIZE IS THE CONNECTION TO GREASE TRAP?
 -CITY WOULD LIKE THE CLEANOUT IN THE ROW.
 -SHOW ALL EXISTING DRY UTILITIES.
 -METER SHOULD BE WITHIN ROW.
 -PLANS APPEAR TO BE CONCEPTUAL. A MORE THOROUGH REVIEW
 WILL BE DONE WITH FINALIZED PLANS.
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
  