| 2021-07-08 10:31:39 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. NO ENGINEERING PLANS (PAVING, GRADING, DRAINAGE) |
| | WERE PROVIDED. |
| | |
| | 2. CONSIDER REDUCING LENGTH OF THE ANGLED PARKING |
| | SPACES BY PROVIDING 2 FEET OF LANDSCAPED OVERHANG, IF |
| | NOT INCLUDED IN THE CURRENT DESIGN. |
| | |
| | 3. PROVIDE THE ANGLE FOR THE ANGLED PARKING SPACES. |
| | |
| | 4. LIST THE VERTICAL DATUM ON EVERY SHEET WITH |
| | ELEVATION INFORMATION. PROVIDE THE CONVERSION EQUATION |
| | TO NGVD1929 IF DATUM IS DIFFERENT. |
| | |
| | 5. PROVIDE A CROSS SECTION FROM THE EAST PARCEL LINE TO |
| | THE FACE OF THE BUILDING SHOWING SURFACE FEATURES AND |
| | TYPICAL PAVEMENT SLOPES. |
| | |
| | 6. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP MODIFICATION BEFORE |
| | THE START OF CONSTRUCTION. |
| | |
| | 4. DRAINAGE CALCULATIONS WILL BE REVIEWED WITH THE |
| | ENGINEERING PERMIT APPLICATION. |
| | |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |