Date Text
2021-07-02 12:17:151. THE CITY OF WEST PALM BEACH HAS A NUMBER OF
 REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY
 AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND
 WASTEWATER UTILITIES WITHIN THE CITY. TO VIEW
 DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AND OTHER
 ENGINEERING RELATED DOCUMENTS, CLICK HERE OR GO TO: HTT
 PS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-FOR
 MS-PERMITS-AND-APPLICATIONS .
 2. CODE OF ORDINANCES, CITY OF WEST PALM BEACH,
 FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08, ADOPTED
 SEPT. 22, 2008. (SUPPLEMENT NO. 18) CHAPTER 90
 UTILITIES, ARTICLE I. SEC. 90-7.
 POLICY REGARDING EXTENSION OF WATER OR SEWER SERVICE
 FACILITIES OF THE CITY:
 THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE
 CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY
 BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS,
 BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION.
 3. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, CLICK HERE OR GO TO: HTTPS://WWW.WPB.
 ORG/GOVERNMENT/ENGINEERING/ENGINEERING-FORMS-PERMITS-AN
 D-APPLICATIONS .
 4. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1040 FOR FURTHER
 ASSISTANCE.
 5. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS
 OF ALL WATER, STORMWATER, AND SANITARY AND SEWER LINES,
 INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND
 SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES,
 METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE
 SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING
 GRADES, PIPES SIZES, MATERIALS, ELEVATIONS,
 ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL
 INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER
 LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN
 VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS.
 PLEASE SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL
 EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT,
 INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES LOCATED ON THE
 RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL
 UTILITY CROSSINGS.
 6. CUT AND CAP UTILITIES NOT IN USE, AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 ROW.
 7. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE
 DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB
 DEVELOPMENT APPLICATION).
 8. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER.
 9. SHOW VERTICAL DATUM AND DATUM CONVERSION INFORMATION
 (NAVD 88 AND NGVD 29).
 10. PLEASE ADD NOTE TO PLANS SPECIFYING CITY?S
 DOWNSTREAM LIFT STATION NUMBER.
 11. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED
 AREAS.
 12. PLEASE LABEL WATER LINES AS PRIVATE WHERE
 APPLICABLE.
 13. ON SHEET EKRA-02 1 OF 2 AND 2 OF 2, THERE IS A 2?
 PROPOSED FM. THE DETAIL SHOWS A PROPOSED 4? FM
 CONNECTING TO AN EXISTING 16? DIP FM. CLARIFY IF 2? OR
 4?.
 14. ON SHEET EKRA-02 1 OF 2 AND 2 OF 2, PLEASE LABEL
 LENGTH AND SIZE OF PROPOSED FM.
 15. ON ALL UTILITY PLAN SHEETS, PLEASE LABEL ?PROPOSED?
 OR ?EXISTING? FOR ALL WATER AND SEWER UTILITIES.
  
 THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD
 CUSTOMER SERVICE SUPERVISOR, WPB PUBLIC UTILITIES,
 PLEASE CONTACT 561-494-2262 OR [email protected]:
  
 -VERIFY FPL WILL OWN AND MAINTAIN THE ENTIRETY OF THE
 PROPOSED 2 INCH FORCE MAIN.
 -SHOW AND LABEL WELL AND LIFT STATION ON SITE PLAN.
 -FPL MUST COMPLY WITH WPB UTILITY BILLING REQUIREMENTS
 FOR WASTEWATER.
 -WILL WELL BE USED FOR IRRIGATION AND ALSO FOR POTABLE
 WATER ON SITE?
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING
 SERVICES, (561) 494-1098 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved