| 2021-06-02 09:54:42 | 1. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY |
| | OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC |
| | RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF |
| | YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE |
| | MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL |
| | IN THE WPB ENGINEERING SERVICES DEPARTMENT AT |
| | [email protected] OR 561-494-1040 FOR FURTHER |
| | ASSISTANCE. |
| | 2. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS |
| | OF ALL WATER, STORMWATER, AND SANITARY AND SEWER LINES, |
| | INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND |
| | SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES, |
| | METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE |
| | SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING |
| | GRADES, PIPES SIZES, MATERIALS, ELEVATIONS, |
| | ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL |
| | INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER |
| | LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE |
| | PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN |
| | VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. |
| | PLEASE SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT |
| | MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL |
| | EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT, |
| | INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION & |
| | TELECOMMUNICATION FACILITIES LOCATED ON THE |
| | RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL |
| | UTILITY CROSSINGS. |
| | 3. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE |
| | DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB |
| | DEVELOPMENT APPLICATION). |
| | 4. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND |
| | IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED |
| | AREAS. |
| | |
| | THE FOLLOWING COMMENTS ARE FROM MARK HURLEY: |
| | |
| | -SHOW EXISTING WATER METER BOX AND BACKFLOW ASSEMBLY |
| | NEAR SOUTH SIDE OF PROPERTY ON SITE PLAN AND CIVIL |
| | PLANS. |
| | |
| | -PLEASE VERIFY HOW EXISTING WATER SERVICE IS CURRENTLY |
| | USED, AND IF USE WILL CHANGE WITH PROPOSED PROJECT. |
| | |
| | -DOES THE FPL PROPERTY CURRENTLY HAVE ANY EXISTING |
| | SEWER LATERALS, AND WILL ANY NEW ONES BE NEEDED? |
| | |
| | -WILL THE CHARGING STATION NEEDED METERED DOMESTIC, |
| | IRRIGATION, OR FIRE WATER SERVICE? |
| | |
| | -IF EXISTING WATER METER WILL REMAIN IN SAME LOCATION, |
| | GRANT UTILITY EASEMENT FOR IT. |
| | |
| | -WILL THE METERED PARKING SPOTS ON DATURA REMAIN? |
| | |
| | -ON THE CIVIL PLANS, LABEL THE ROW OR CITY WPB PROPERTY |
| | AT QUADRILLE PLAZA DR. |
| | |
| | -WILL THE PARKING SPOTS FIT THE DIMENSIONS OF THE NEW |
| | ELECTRIC TRUCKS BEING PRODUCED SUCH AS THE FORD |
| | LIGHTNING? |
| | |
| | -WHAT WILL THE EMPTY PAVED AREA ON WEST SIDE OF THE |
| | CHARGING STATION AREA BE USED FOR? |
| | |
| | -THE FENCE ON WEST SIDE SAID REMOVEABLE. WHEN WOULD IT |
| | BE REMOVED, AND WOULD A KEY BE NEEDED FOR REMOVAL? |
| | |
| | RESPECTFULLY, |
| | MARK HURLEY, FIELD CUSTOMER SERVICE SUPERVISOR |
| | CITY OF WEST PALM BEACH PUBLIC UTILITIES, 561-822-2262, |
| | [email protected] |
| | |
| | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| | CONCERNS, THANKS. |
| | RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES |
| | DEPARTMENT, (561) 494-1098 [email protected] |
| | |
| | |
| | |
| |