Plan Review Notes For Project Z21040017
Project Number Z21040017
Review Stop ENG - PPRC
Sequence Number 3
Notes
Date Text
2021-12-22 09:25:04COMMENTS PER RICK ROSSANO, PROJ. COORD. WPB ENG.
 SERVICES, [email protected], 561-494-1098:
 1. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 2. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED
 AREAS.
 3. FOR FORMAL ENGINEERING SUBMITTAL , PLANS SHALL SHOW
 PROPOSED LOCATIONS AND DIMENSIONS OF ALL WATER,
 STORMWATER, AND SANITARY AND SEWER LINES, INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, METERS, AND
 OTHERS DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. ALL
 AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE VIEW.
 DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN
 VIEW FOR ALL SANITARY AND STORM SEWERS. ADDITIONALLY,
 PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES LOCATED ON THE RIGHT-OF-WAY.
 4. FOR FORMAL ENGINEERING SUBMITTAL, CUT AND CAP
 UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY
 LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY.
 5. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND
 NPDES NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE; AND
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION. IF THE ENGINEERING PLANS DO
 NOT INCLUDE AN EROSION CONTROL PLAN, THEN THE
 CONTRACTOR SHOULD SUBMIT ONE PRIOR TO RECEIVING THE
 ENGINEERING PERMIT.
 6. PROVIDE PROFILES OF PROPOSED AND EXISTING WATER AND
 SEWER WITHIN RIGHT OF WAY AND SHOW ANY
 CROSSINGS/CONFLICTS.
 7. CLEARLY LABEL ROAD RIGHT OF WAY.
 8. PLEASE SHOW REPLACEMENT OF SANITARY LATERALS AND
 SHOW ADDRESSES OF ADJACENT PARCELS.
 9. PLEASE SHOW WATER SERVICES/METERS ETC. AND ADJACENT
 PARCEL ADDRESSES.
 10. WHEN TRENCHING IN IN CITY-MAINTAINED ROADWAY AREAS
 ADD NOTE TO PROVIDE 50 FT. PAVEMENT RESTORATION
 TRANSITION ON EACH SIDE OF PROPOSED TRENCH PER CURRENT
 CITY OF WPB STANDARD DETAIL GC-8.
 11. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (Z-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE SUPV.
 WPB PUB. UTIL. 561-494-2262 OR [email protected]:
  
 DID NOT RECEIVE RESPONSE TO PRIOR REVIEW COMMENTS.
 PLEASE PROVIDE WRITTEN RESPONSE:
  
 -WATER MAIN TEES AT INTERSECTIONS NEED ADDITIONAL GATE
 VALVES FOR THE BRANCHES.
  
 -SOME WATER SERVICES AND METER BOXES APPEAR TO BE
 MISSING FROM CIVIL PLANS SUCH AS 1147 N RAILROAD AND
 1021 N RAILROAD.
  
 -FOR FORMAL ENGINEERING SUBMITTAL, SHOW AND DETAIL MORE
 CLEARLY THE WATER MAIN CONNECTIONS FROM NEW 12 INCH
 WATER MAIN TO THE EXISTING WATER MAINS. INCLUDE INFO ON
 ANY PARTS, REDUCERS, VALVES, ETC.
  
 -MANY SECTIONS OF SEWER MAIN SAY 0.42% BUT ONE NEAR
 10TH AND RAILROAD SAYS 4.42%. IS THAT ACCURATE?
  
 -THERE ARE TRAFFIC SIGNS ATTACHED TO WOOD UTILITY POLE
 AT 11TH AND N RAILROAD. WILL THE UTILITY UNDERGROUNDING
 AFFECT THIS?
  
 -THERE ARE MANY GARAGES WITH DRIVEWAYS. HOW WILL THIS
 BE HANDLED? WILL THEY ALL STILL BE USABLE AT PROJECT
 COMPLETION, AND HAS THE PROJECT DESIGN MADE SURE
 PROPOSED TREES WILL NOT IMPEDE USE?
  
 -SEVERAL UTILITIES SUCH AS S113, S111, AND S107
 ENCROACH SLIGHTLY INTO PLANTERS. WILL THIS CAUSE
 PROBLEM?
  
 -S113 AND S110 ARE IN A CROSSWALK. WILL THESE CREATE
 ANY TRIP AND FALL HAZARDS OR PROBLEMS WITH USE OF
 CROSSWALK?
  
 -CANNOT TELL FROM PLANS IF SEWER MAIN ALONG THE WEST
 SIDE OF RAILROAD AVENUE UNDER THE SIDEWALK IS EXISTING
 OR PROPOSED AND WHAT IS HAPPENING TO IT. PLEASE MAKE
 MORE CLEAR.
  
 -ARE THERE ANY EXISTING OR PROPOSED SEWER LATERAL
 CLEANOUTS IN PROJECT AREA? IF SO, PLEASE SHOW AND
 LABEL.
  
 -THERE IS AN EXISTING LIGHT POLE AT PROPOSED NORTH
 DRIVEWAY OF PARKING LOT ON 9TH ST. WHAT IS HAPPENING TO
 IT?
  
 -ON IRRIGATION PLAN, REPLACE PVB TYPE BACKFLOW ASSEMBLY
 WITH RP TYPE.
  
 -THERE ARE EXISTING UTILITY POLES AND GUY WIRES IN
 ALLEY BETWEEN 8TH AND 9TH ST. ARE THOSE BEING
 UNDERGROUNDED?
  
 -FOR FORMAL ENGINEERING SUBMITTAL: LABEL SEWER LATERALS
 WITH PIPE SIZE AND MATERIAL TYPE, SHOW ALL FRANCHISE
 UTILITIES INCLUDING GAS AND FIBER OPTIC, CALLOUT ALL
 UTILITY CROSSINGS IN CLOSE PROXIMITY WITH ELEVATION
 INFO.
  
 -AT 10TH ST INTERSECTION, ONE WATER MAIN VALVE IS IN A
 CROSSWALK AND ONE FIRE HYDRANT SERVICE GATE VALVE IS IN
 A CROSSWALK. CAN BOTH BE RELOCATED OUTSIDE OF SIDEWALK?
  
 -WILL A FORCE MAIN OR SEWER MAIN RUN THROUGH PROPOSED
 PARKING LOTS? IF SO, PLEASE SHOW ON CIVIL PLANS.
  
 -WHAT ARE THE LARGE STRIPED AREAS JUST NORTH OF 10TH ST
 INTERSECTION? ARE THEY RAISED AND CURBED, OR LEVEL WITH
 THE STREET?
  
 -ARE THERE ANY PROPOSED GREASE TRAPS? IF SO, SHOW ON
 PLANS.
  
 -IS THE ENTIRETY OF NORTH RAILROAD AVENUE STREET FROM
 7TH ST TO 11TH ST BEING REPAVED WITH ASPHALT? CANNOT
 TELL FROM PLANS. PLEASE SHOW AND LABEL THE GENERAL
 OUTSKIRT BOUNDARIES OF THE PAVEMENT RESTORATION. ALSO
 INCLUDE ANY SIDESTREETS AND ALLEYS.
  
 -SOME BUILDING DOORS SUCH AS 917 AND 861 N RAILROAD
 LOOK TO OPEN OUTWARD INTO SIDEWALK. PLEASE SHOW ALL THE
 BUILDING DOORS AND MAKE SURE STREETSCAPE PLAN DESIGN
 WORKS IN UNISON WITH ANY DOORS.
  
  
 COMMENTS FROM MIKE TECHNOW, PUB. UTIL. ENGINEER,
 561-494-1047, [email protected] :
  
 -RECOMMEND TO GROUT THE EXISTING 8? SANITARY MAIN (ON
 THE EAST SIDE).
 -REPLACE STORMWATER PIPE ON 10TH ST/NORTH RAILROAD AS
 PART OF THE UTILITY IMPROVEMENTS.
 -REPLACE EXISTING SANITARY SERVICES, CALL OUT/SHOW
 CLEAN OUTS, WYES, SHOW CONNECTION TO NEW MAIN.
 -REDUCE WM TO 4? AT CONNECTION POINT.
 -SHOW DRY UTILITY CROSSING.
 -REPLACE EXISTING FIRE HYDRANTS.
 -CALL OUT NEW WATER SERVICES AND REPLACEMENTS.
 -CALL OUT SIZE OF WATER SERVICE.
 -SHOW EXISTING AND PROPOSED DRY UTILITIES (FPL
 UNDERGROUND).
 -SHOW WM PROFILE.
 -PROVIDE LEVEL OF SERVICE CALCS FOR PROPOSED
 DEVELOPMENT.
 -ARE THERE ANY LANDSCAPE PLANS?
  
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 DIRECT: (561) 494-1098 [email protected]
  