Plan Review Notes
Plan Review Notes For Project Z21030022
Project Number Z21030022
Review Stop TRAFFIC
Sequence Number 2
Notes
Date Text
2021-05-07 11:26:14TRAFFIC COMMENTS
 1) SATISFIED. PROVIDE COUNTY TPS LETTER
 2) NOT SATISFIED. PER COUNTY RECOMMENDATION, ANALYZE
 IMPLEMENTATION OF A RIGHT-RUN LANE FROM FOREST HILL
 BLVD TO GEORGIA AVE ALONG THE WEST APPROACH.
 3) PARTIALLY SATISFIED. PROVIDE AUTOTURN ANALYSIS
 SHOWCASING GARBAGE TRUCK AND SERVICE VEHICLES PATHS IN
 AND OUT OF THE FACILITY. LATEST SUBMISSION SHOWCASES
 ENCROACHMENT AT THE ACCESS DRIVEWAY.
 4) NOT SATISFIED. IS THE PERFORMANCE CENTER PART OF THE
 DEVELOPMENT? IF SO, PLEASE INCLUDE ITS IMPACT IN THE
 TRAFFIC STUDY
  
 SITE COMMENTS
 5) NOT SATISFIED. INSTALL PEDESTRIAN REFUGEE ISLAND AT
 THE ACCESS DRIVEWAY
 6) NOT SATISFIED. DRIVEWAY ENTRY AND EXIT LANE CAN?T BE
 MORE THAN 12 FEET WIDE. A PEDESTRIAN REFUGEE ISLAND
 SHOULD BE IMPLEMENTED IN ORDER TO MITIGATE THE PROPOSED
 20 FEET WIDE OUTBOUND LANE.
 7) NOT SATISFIED. GIVEN THE WIDTH OF THE PROPOSED
 OUTBOUND LANE, IT IS RECOMMENDED TO SPLIT IT INTO TWO
 10-FOOT LANES AND INSTALL PAVEMENT MARKINGS FOR
 LEFT-ONLY AND RIGHT-ONLY MOVEMENTS
 8) NOT SATISFIED. PROVIDE BICYCLE FACILITIES ACCORDING
 TO CITY MASTER PLAN
 O BIKE LANES/MULTIUSE PATH ALONG GEORGIA AVE/GREGORY RD
 O SHARROW ALONG MADDOCK ST
 O TRAIL THROUGH OR AROUND THE PROPOSED GOLF COURSE
 STARTING FROM GREGORY RD, ALONG THE SOUTH SIDE CANAL
 THEN HEADING NORTH PARALLEL TO I-95
 9) NOT SATISFIED. IF A SIDEWALK OR MULTIUSE PATH IS
 ESTABLISHED ON THE WEST SIDE OF GEORGIA AVE, EXTEND IT
 ALONG THE SOUTH SIDE OF GREGORY RD TO THE RR TRACKS AND
 PROVIDE A CROSSWALK TO CONNECT TO THE NORTH SIDE
 SIDEWALK
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  