Notes
Date Text
2021-04-08 08:46:16THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
  
 1. ADD SCALE BAR TO THE GOLFCOURSE AND CLUBHOUSE
 ENGINEERING PLANS TO FACILITATE REVIEWING PLANS ON THE
 COMPUTER.
  
 2. UPDATE THE UTILITIES SHOWN ON THE CLUBHOUSE SITE
 PLAN AND LANDSCAPE PLANS TO SHOW WHAT IS SHOWN ON THE
 ENGINEERING PLANS.
  
 3. SHOW THE EXISTING 60? STORM PIPE AND ANY OTHER
 EXISTING UTILITIES ON THE LANDSCAPE PLANS.
  
 4. CONSIDER REDUCING THE LENGTH OF PARKING SPACES BY
 TWO FEET AND PROVIDE TWO FEET OF LANDSCAPED AREA
 OVERHANG.
  
 5. ADD ADDITIONAL SPOT GRADES, CONTOURS OR CROSS
 SECTIONS TO THE CLUBHOUSE PGD PLANS TO INDICATE HOW THE
 DEVELOPMENT WILL MEET EXISTING GRADES.
  
 6. CONFIRM THESE IS NOT AN OUTFALL PIPE FOR THE
 CLUBHOUSE DRAINAGE SYSTEM.
  
 7. CONSIDER COMBINING THE TWO INLETS AT THE CLUBHOUSE
 ENTRANCE AS ONE CATCH BASIN INLET IN THE LANDSCAPED
 MEDIAN WITH FLUMES TO GET THE STORMWATER RUNOFF INTO
 THE MEDIAN.
  
 8. DRAINAGE STRUCTURES UPSTREAM AND DOWNSTREAM OF
 EXFILTRATION TRENCHES SHOULD HAVE PRB?S TO PROLONG THE
 USEFUL LIFE OF THE EXFILTRATION TRENCHES.
  
 9. LABEL THE SOIL CONTAMINATION AREA ON SHEET GP-7.
  
 10. SHOW AND LABEL THE SPOIL PILE EASEMENT, SFWMD C-51
 SEDIMENT PROJECT EASEMENT AND SFWMD ACCESS EASEMENT ON
 SHEETS GP-7 AND GP-8.
  
 11. ENSURE THE IMPROVEMENTS AND GRADING WITHIN THE
 SFWMD EASEMENTS WILL NOT RESTRICT ACCESS TO THE
 EASEMENTS AND SPOIL PILE EASEMENT.
  
 12. PROVIDE A DETAIL OF THE CONTROL STRUCTURE FOR THE
 PROPOSED LINED LAKE.
  
 13. WILL SUPPLEMENTAL WATER BE ADDED TO THE PROPOSED
 LINED LAKE DURING THE DRY SEASON TO MAINTAIN THE
 LITTORAL PLANTINGS?
  
 14. ON SHEET ESC:
 A. SHOW PROTECTION OF THE CATCH BASIN IN THE EXISTING
 DRY DETENTION AREA IN THE SOUTHEAST CORNER OF THE SITE.
 B. SHOW FLOATING TURBIDITY BARRIER ON THE EXISTING AND
 PROPOSED OUTFALLS IN THE C-51 CANAL.
  
 15. THE GOLF COURSE DRAINAGE CALCULATIONS SUMMARY PAGE
 LISTS THE 5-YR 1-DAY POST-DEVELOPMENT PEAK STAGE BUT
 THIS DESIGN STORM DOES NOT APPEAR IN THE ANALYSIS.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE COPY OF MODIFIED SFWMD ERP PERMIT(S) BEFORE
 START OF CONSTRUCTION.
  
 4. PROVIDE A COPY OF THE DRAINAGE CALCULATIONS WITH THE
 ENGINEERING PERMIT APPLICATION. DRAINAGE SYSTEMS TO BE
 DESIGNED TO MEET SFWMD ERP CRITERIA.
  
 5. PERMIT WILL BE NEEDED FROM SFWMD TO WORK WITHIN THE
 C-51 CANAL R/W.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  