| 2021-02-05 14:52:06 | INCLUDES PB CASE NO.'S 1876 AND 1877. | | | | | | 1. SURVEY NEEDS TO BE SIGNED AND SEALED. | | | 2. NEED SEPARATE S & S COPIES OF SKETCH AND LEGALS FOR | | | ABANDONMENTS. NEED SIGN-OFFS FROM ALL UTILITIES. | | | 3. APPRAISALS WILL BE REQUIRED AND WILL BE ORDERED | | | AFTER RECEIPT OF PAYMENT. QUOTE WILL BE REQUESTED AFTER | | | FURTHER REVIEW. | | | 4. REPLAT WILL BE REQUIRED. LIMITS TO BE DETERMINED. | | | 5. REVIEW OF EXISTING DRAINAGE IS NEEDED. ENG. PLANS | | | SHOW DRAINAGE INTO FEC R/W WHICH DIFFERS FROM GIS. | | | 6. ADD CONVERSION TO NGVD TO SURVEY AND ENGINEERING | | | PLANS. | | | 7. UTILITY AND/OR DRAINAGE EASEMENTS WILL NEED TO BE | | | RESERVED. | | | 8. MAY NEED TO ADJUST BUILDING DUE TO PROXIMITY WITH | | | 20" WATER MAIN. | | | | | | |
| |