| Plan Review Notes For Project Z21010025 |
| Project Number |
Z21010025 |
|
| Review Stop |
ENG - PPRC |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2021-04-27 10:55:49 | COMMENTS PER RICK ROSSANO, PROJ. COORD. WPB ENG. | | | SERVICES, [email protected], 561-494-1098: | | | 1. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER | | | (CONDITION OF SITE PLAN APPROVAL). STORMWATER APPEARS | | | TO BE ONSITE ONLY; IF SO, NO CCTV OF CITY STORMWATER | | | INFRASTRUCTURE ALONG PROJECT FRONTAGE IS NEEDED.) | | | | | | COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE SPV., | | | CITY OF WPB PUB. UTILITIES, 561-822-2262, | | | [email protected] | | | -BACKFLOW ASSEMBLY MAY NOT BE LOCATED IN A UTILITY | | | EASEMENT. ONE WAY TO RESOLVE WOULD BE ADJUSTING | | | BOUNDARIES/DIMENSIONS OF PROPOSED UTILITY EASEMENT. | | | |
| |