2021-02-11 18:57:43THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. CONSIDER REDUCING THE DEPTH OF THE PARKING BY 2 FEET
 AND PROVIDE LANDSCAPE OVERHANG.
  
 2. MOVE S-102 FURTHER FROM THE BACK OF SIDEWALK WITH
 THE GRATE ELEVATION LOWER THAN THE BACK OF SIDEWALK
 ELEVATION TO ENSURE THE STORMWATER RUNOFF IS CAPTURED
 IN THE SYSTEM.
  
 3. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA.
  
 4. REPLACE SIDEWALK ADJACENT TO THE DRIVEWAY APRON WITH
 6? THICK SIDEWALK PER CITY DETAILS.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 4. DRAINAGE CALCULATIONS WILL BE REVIEWED WITH THE
 ENGINEERING PERMIT APPLICATION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved