| 2021-12-21 12:43:04 | 1. TREES ALONG LAKEVIEW AVE AND OKEECHOBEE AVE SHALL BE |
| | MOVED OUTSIDE THE PARKING GARAGE LINE OF SIGHT. A |
| | MINIMUM OF 12 FEET MULTIPURPOSE PATH SHALL BE |
| | MAINTAINED. SOME ADJUSTMENT WILL BE NEEDED ON THE |
| | PROPOSED LANDSCAPE DESIGN ADJACENT TO THE OFFICE TOWER |
| | TO ACCOMMODATE THE LINE OF TREES. |
| | 2. SIDEWALK LEVEL SHALL BE MAINTAINED ACROSS ALL THE |
| | DRIVEWAYS. PLEASE AJUST THE CIVIL DESIGN TO ENSURE THE |
| | GRADE ELEVATION IS MAINTAINED. |
| | 3. PARKING GATE IS LOCATED AT THE 2ND LEVEL. WHAT IS |
| | THE PROPOSAL FOR RETAIL AND VALET PARKING? STAFF |
| | RECOMMENDS THE GATE TO BE INSTALLED AT THE 3RD LEVEL TO |
| | ALLOW PARKING FOR CUSTOMERS OR EXPLAIN INTENDED |
| | OPERATION. |
| | 4. HOW IS THE 2ND LEVEL OFFICE ALONG THE PASEO ACCESSED |
| | FROM THE ELEVATOR? PLEASE VERIFY COMPLIANCE WITH |
| | EMERGENCY EXIT REQUIREMENTS. |
| | 5. VALET OPERATION DOES NOT PROVIDE A BY-PASS LANE |
| | CREATING A POSSIBLE BACK UP FOR CARS. SOME REDESIGN MAY |
| | BE NEEDED. |
| | 6. ALL TANDEM PARKING SPACES SHALL BE MANAGED BY THE |
| | VALET OPERATION. PLEASE LABEL ACCORDINGLY. |
| | 7. PLEASE LABEL THE LOCATION OF ALL CAR SHARE AND RIDE |
| | SHARE SPACES REQUIRED BY THE TDM STRATEGIES. |
| | 8. PLEASE CONFIRM COMPLIANCE WITH OPEN SPACE |
| | REQUIREMENTS FOR VEGETATION AND TREE CANOPY. THE |
| | CALCULATION CAN BE DONE OVER A MINIMUM AREA TO COMPLY |
| | WITH THE PERCENTAGE AND NOT THE LARGER OPEN SPACE |
| | PROVIDED. (SEE LANDSCAPE COMMENTS) |
| | 9. BUILDING FOOTPRINT PRIVIDED ON SHEET A004 DOES NOT |
| | MATCH THE WAIVER REQUEST, PLEASE CONFIRM WHAT IS THE |
| | CORRECT NUMBER. |
| | 10. PLEASE PROVIDE AN EXHIBIT TO CALCULATE THE PROVIDED |
| | ACTIVE USES AT GROUND FLOOR AND ABOVE TO CONFIRM WAIVER |
| | REQUEST. |
| | FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA |
| | APONTE AT 561-822-1439. |
| |