Plan Review Notes
Plan Review Notes For Project Z20120016
Project Number Z20120016
Review Stop STORM
Sequence Number 1
Notes
Date Text
2021-01-14 13:37:46THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
  
 1. VERIFY THE SIGN (POSITIVE/NEGATIVE) OF THE
 CONVERSION FACTOR BETWEEN NAVD1988 AND NGVD1929
 VERTICAL DATUMS.
  
 2. LIST THE WATER TABLE ELEVATION AS NAVD1988 WITH
 NGVD1929 IN PARENTHESES.
  
 3. THE LISTED WATER TABLE ELEVATION APPEARS TOO LOW
 GIVEN THE DISTANCE TO THE LAKE WORTH LAGOON. FIELD
 VERIFY THE WET SEASON WATER TABLE ELEVATION. (CAN BE
 PROVIDED DURING ENGINEERING PERMIT APPLICATION).
  
 4. PROVIDE TYPICAL CROSS SECTIONS FROM CENTERLINE OF
 ADJACENT ROADS TO BUILDING FACE AND BETWEEN THE
 BUILDING AND PARKING GARAGE. SHOW AND LABEL THE RIGHT
 OF WAY LINES AND TYPICAL PROPOSED SLOPES.
  
 5. HOW WILL BOTTOM FLOOR OF THE PARKING GARAGE DRAIN?
  
 6. ADD THE DIFFERENT SPOT GRADE SYMBOLS TO THE SHEET
 LEGEND OF SHEET CG101.
  
 7. SHOW UTILITIES ON THE LANDSCAPE PLANS AND HARDSCAPE
 PLANS.
  
 8. SHOW ADA TACTILE SURFACES FOR CURB RAMPS ON THE
 HARDSCAPE PLANS.
  
 9. SHOW AND CALLOUT PERIMETER PLANTER AREAS ON THE
 ENGINEERING PLANS.
  
 10. PERIMETER PLANTER AREA AT NORTHWEST CORNER OF THE
 SITE EXTENDS PAST THE CROSSWALK.
  
 11. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP
 CRITERIA.
  
 12. NOTE BLEEDERS ARE NOT PERMITTED AS PART OF THE
 CONTROL STRUCTURE USED TO SURCHARGE EXFILTRATION
 TRENCHES.
  
 13. SHOW MILL AND RESURFACING LIMITS FOR THE TRENCH
 CUTS ON THE PGD PLAN.
  
 14. INDICATE WHICH DRAINAGE STRUCTURES AND SIDES WILL
 HAVE PRB'S.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. A SFWMD ERP MAY BE REQUIRED. PROVIDE A COPY OF THE
 PERMIT PRIOR TO STARTING CONSTRUCTION.
  
 4. PROVIDE A COPY OF THE DRAINAGE CALCULATIONS WITH THE
 ENGINEERING PERMIT APPLICATION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved