| 2020-12-10 13:21:48 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. DRAINAGE SYSTEM TO BE DESIGNED PER THE MASTER ERP |
| | PERMIT FOR THE SITE. |
| | |
| | 2. PROVIDE THE VERTICAL SEPARATION BETWEEN THE PROPOSED |
| | STORM PIPE AND THE EXISTING STORM PIPE IN THE DRIVE |
| | AISLE ALONG THE EAST SIDE OF THE SITE. |
| | |
| | 3. CAR WASH WATER IS NOT TO BE INTRODUCED INTO THE |
| | DRAINAGE SYSTEM. |
| | 4. SITE IS LOCATED WITHIN A SPECIAL FLOOD HAZARD AREA |
| | (SFHA). STRUCTURES WITHIN A SFHA ARE TO PROVIDE MINIMUM |
| | TWO FEET OF FREEBOARD ABOVE THE BASE FLOOD ELEVATION. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE FDEP ERP MODIFICATION AND |
| | DRAINAGE CALCULATIONS PRIOR TO STARTING CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |