| Plan Review Notes For Project Z20100020 |
| Project Number |
Z20100020 |
|
| Review Stop |
SURVEY |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2020-12-07 08:06:09 | 1. NEED SIGNED AND SEALED SURVEY BY A REGISTERED LAND | | | SURVEYOR. | | | 2. PLEASE COORDINATE WITH VLADIMIR JEANNOT IN | | | ENGINEERING FOR PROPOSED TAMARIND AVE. | | | 3. THE UTILITY EASEMENT IS ACTUALLY AN FPL EASEMENT PER | | | ORB 27819/1951. THERE IS ANOTHER FPL EASEMENT IN THE NE | | | CORNER PER ORB 29015/1709. BOTH ARE PROPOSED TO HAVE AN | | | 8' X 8' TRANSFORMER. | | | 4. UNITY OF TITLE WILL BE REQUIRED. | | | 5. NEED APPROVED PLAN BY FPL FOR ANY RE-ROUTING PRIOR | | | TO SITE PLAN APPROVAL. | | | 6. IS THE SOUTH EXIT PROPOSED TO BE GATED? |
| |