Plan Review Notes
Plan Review Notes For Project Z20070016
Project Number Z20070016
Review Stop STORM
Sequence Number 2
Notes
Date Text
2021-03-17 02:46:04THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 2/24/2021 SUBMITTAL:
  
 1. ON THE DRAINAGE PLAN, PROVIDE PIPE SIZES AND PIPE
 MATERIAL FOR EXISTING STORM PIPES, SEWER MAINS, FORCE
 MAINS AND WATER MAINS.
  
 2. CHECK PIPE COVER FOR PIPES WITHIN THE PROPOSED DRY
 DETENTION AREAS.
  
 3. REVIEW GRATE ELEVATION OF 14.80? NAVD FOR CATCH
 BASIN LOCATED IN NORTH DRIVEWAY. DRIVEWAY CROSS SLOPE
 WOULD BE AROUND 3.5% AND LONGITUDINAL SLOPE AROUND 2%.
 CONSIDER FLUME INTO THE DRY DETENTION AREA INSTEAD OF
 THIS CATCH BASIN.
  
 4. THE STORM PIPE FROM BEST BUY IS SHOWN AS A SANITARY
 PIPE AND MAY NOT BE SHOWN IN THE CORRECT LOCATION. THE
 PIPE FROM THE SOUTHEAST CORNER OF BEST BUY IS LIKELY IN
 THE 12? DRAINAGE EASEMENT AND EITHER CONNECTS TO THE
 MANHOLE IN THE DRIVEWAY OR CONTINUES EAST TO THE DITCH
 ON THE OTHER SIDE OF EXECUTIVE CENTER DRIVE. PLEASE
 VERIFY.
  
 5. THE STORM PIPE FROM THE CENTER OF EXECUTIVE CENTER
 DRIVE CONNECTS TO THE MANHOLE IN THE NORTH DRIVEWAY
 INSTEAD OF THE OFFSITE CATCH BASIN.
  
 6. WEIR ELEVATION OF 9.55? NAVD IN THE PROPOSED CONTROL
 STRUCTURE APPEARS LOW BASED ON THE DRY DETENTION POND
 ELEVATION OF 10.50? NAVD.
  
 7. PROVIDE CROSS SECTION OF ROAD WIDENING (RIGHT TURN
 LANE).
  
 8. PROVIDE SPOT GRADES FOR NEW RIGHT TURN LANE AND AT
 DRIVEWAYS.
  
 9. DRY DETENTION AREA IS NOT DEPICTED ON THE WATER MAIN
 PROFILE OR FORCE MAIN PROFILE ON SHEET C503.0.
  
 10. 6? WATER MAIN TO THE FIRE HYDRANT LABELED AS 10?
 WATER MAIN ON THE FORCE MAIN PROFILE.
  
 11. PROVIDE VERTICAL DATUM CONVERSION EQUATION ON THE
 SURVEY.
  
 TRACY WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120 (O)
 561-351-0510 (M)
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved