Plan Review Notes
Plan Review Notes For Project Z20070014
Project Number Z20070014
Review Stop ENG - PPRC
Sequence Number 1
Notes
Date Text
2020-08-06 09:29:091. THE CITY OF WEST PALM BEACH HAS A NUMBER OF
 REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY
 AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND
 WASTEWATER UTILITIES WITHIN THE CITY. PLEASE SEE
 DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AT THE LINK
 BELOW: HTTP://WPB.ORG/CMSPAGES/GETAMAZONFILE.ASPX?PATH=
 ~\WPB_WEBSITE\MEDIA\ENGINEERING\DEVELOPMENT-APPLICATION
 -FULL-PACKAGE_2016.PDF&HASH=7BD4DD7EB6115181D8C5977BCC0
 2A97B1960045731D3658206F27451722716EF
 THIS AND OTHER RELATED ENGINEERING DOCUMENTS CAN BE
 FOUND HERE: HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBL
 IC-WORKS/FORMS,-PERMITS-APPLICATIONS
 2. CODE OF ORDINANCES, CITY OF WEST PALM BEACH,
 FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08, ADOPTED
 SEPT. 22, 2008. (SUPPLEMENT NO. 18)
 CHAPTER 90 UTILITIES, ARTICLE I. SEC. 90-7.
 POLICY REGARDING EXTENSION OF WATER OR SEWER SERVICE
 FACILITIES OF THE CITY.
 THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE
 CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY
 BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS,
 BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION.
 3. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, REFER TO THE LINK BELOW:
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
 4. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1040 FOR FURTHER
 ASSISTANCE.
 5. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS
 OF ALL WATER, STORMWATER, AND SANITARY AND SEWER LINES,
 INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND
 SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES,
 METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE
 SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING
 GRADES, PIPES SIZES, MATERIALS, ELEVATIONS,
 ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL
 INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER
 LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN
 VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS.
 PLEASE SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL
 EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT,
 INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES LOCATED ON THE
 RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL
 UTILITY CROSSINGS.
 6. CUT AND CAP UTILITIES NOT IN USE, AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 ROW.
 7. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE
 DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB
 DEVELOPMENT APPLICATION).
 8. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 FOR WATER.
 9. SHOW VERTICAL DATUM AND DATUM CONVERSION INFORMATION
 (NAVD 88 AND NGVD 29).
 10. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED
 AREAS.
 11. PLEASE LABEL WATER LINES AS PRIVATE WHERE
 APPLICABLE.
 12. PLEASE PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED
 LOCATION OF WATER METER AND BACKFLOW PREVENTION, IF
 ANY.
 13. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 14. PROVIDE DEDICATED UTILITY EASEMENTS TO ALLOW ACCESS
 FOR CITY PERSONNEL TO PROPOSED UTILITY WATER METERS AS
 NEEDED.
  
 THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD
 CUSTOMER SERVICE SUPERVISOR, WPB PUBLIC UTILITIES,
 PLEASE CONTACT 561-494-2262 OR [email protected]:
  
 -WATER SERVICE SHOWN ON C-400 ENGINEERING PLAN IS ALL
 PRIVATE WATER PIPE. THE POINT OF SERVICE IS LIKELY THE
 1 IN. CITY WATER METER THAT IS ADJACENT BRANDYWINE RD.
 PROVIDE WATER DEMAND CALC. CHART ON THE PLAN TO ENSURE
 PROPERTY WILL HAVE SUFFICIENT WATER.
 -SEVERAL YEARS AGO WASTEWATER USE WAS TERMINATED AT THE
 LOCATION BECAUSE CUSTOMER SAID THEY WERE GOING TO
 RECYCLE THE WATER USED AT THE EQUIPMENT CLEANING
 STATION WITH A WATER FILTRATION BASIN. PLEASE SHOW ON
 PLAN WHERE THAT IS LOCATED AND VERIFY IF THAT WILL
 STILL BE USED FOR THE SITE WITH NO WASTEWATER GOING TO
 CITY.
 -NEED VERIFICATION THAT THE WATER SERVICE WILL NOT FEED
 FIRE SPINKLERS OR HYDRANTS.
 -PLEASE VERIFY THAT THE EXISTING WATER SERVICE PIPING
 ON C-400 IS POTABLE WATER PIPE RUNNING FROM CITY WATER
 SERVICE AND NOT NON-POTABLE WATER FROM WELLS OR
 SURROUNDING PUMPED GROUNDWATER.
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 DIRECT: (561) 494-1098 [email protected]
  