| Plan Review Notes For Project Z20050013 |
| Project Number |
Z20050013 |
|
| Review Stop |
TRAFFIC |
| Sequence Number |
4 |
|
| Notes |
| Date |
Text |
| 2021-05-03 18:43:36 | PASSED WITH THE FOLLOWING CONDITIONS TO BE FULFILLED | | | PRIOR TO THE ISSUANCE OF CERTIFICATE OF OCCUPANCY: | | | | | | 1) AGREED TDM STRATEGIES NEED TO BE FURTHER ELABORATED | | | AND AN ANNUAL REPORT PROVIDED FOR THE FIRST 5 YEARS OF | | | OPERATION/IMPLEMENTATION | | | 2) PER THE BICYCLE SHARING PROGRAM, PROVIDE A TIMELINE | | | AND DETAILS PERTAINING NUMBER OF BIKES, | | | PICK-UP/DROP-OFF/STORAGE LOCATIONS AND MAINTENANCE PLAN | | | 3) PER THE RIDESHARING, SHOWCASE AND LABEL THE | | | DEDICATED PARKING SPACES ON THE FINAL SITE PLAN | | | 4) PER THE 4 ELECTRIC VEHICLE CHARGING STATION, | | | SHOWCASE AND LABEL THE DEDICATED SPACES ON THE FINAL | | | SITE PLAN | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
| |