| 2021-05-06 12:27:02 | COMMENTS PER RICK ROSSANO, PROJ. COORD. WPB ENG. |
| | SERVICES, [email protected], 561-494-1098: |
| | |
| | 1. THE CITY OF WEST PALM BEACH HAS A NUMBER OF |
| | REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY |
| | AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND |
| | WASTEWATER UTILITIES WITHIN THE CITY. TO VIEW |
| | DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AND OTHER |
| | ENGINEERING RELATED DOCUMENTS, CLICK HERE OR GO TO: HTT |
| | PS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-FOR |
| | MS-PERMITS-AND-APPLICATIONS . |
| | 2. CODE OF ORDINANCES, CITY OF WEST PALM BEACH, |
| | FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08, ADOPTED |
| | SEPT. 22, 2008. (SUPPLEMENT NO. 18) CHAPTER 90 |
| | UTILITIES, ARTICLE I. SEC. 90-7. |
| | POLICY REGARDING EXTENSION OF WATER OR SEWER SERVICE |
| | FACILITIES OF THE CITY: |
| | THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE |
| | CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY |
| | BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS, |
| | BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION. |
| | 3. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH |
| | CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED, |
| | STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR |
| | MORE INFORMATION, CLICK HERE OR GO TO: HTTPS://WWW.WPB. |
| | ORG/GOVERNMENT/ENGINEERING/ENGINEERING-FORMS-PERMITS-AN |
| | D-APPLICATIONS . |
| | 4. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY |
| | OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC |
| | RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF |
| | YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE |
| | MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL |
| | IN THE WPB ENGINEERING SERVICES DEPARTMENT AT |
| | [email protected] OR 561-494-1040 FOR FURTHER |
| | ASSISTANCE. |
| | 5. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS |
| | OF ALL WATER, STORMWATER, AND SANITARY AND SEWER LINES, |
| | INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND |
| | SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES, |
| | METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE |
| | SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING |
| | GRADES, PIPES SIZES, MATERIALS, ELEVATIONS, |
| | ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL |
| | INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER |
| | LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE |
| | PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN |
| | VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. |
| | PLEASE SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT |
| | MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL |
| | EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT, |
| | INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION & |
| | TELECOMMUNICATION FACILITIES LOCATED ON THE |
| | RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL |
| | UTILITY CROSSINGS. |
| | 6. CUT AND CAP UTILITIES NOT IN USE, AND REMOVE ANY |
| | ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY |
| | ROW. |
| | 7. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE |
| | DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB |
| | DEVELOPMENT APPLICATION). |
| | 8. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND |
| | PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM |
| | AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE |
| | PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER. |
| | 9. SHOW VERTICAL DATUM AND DATUM CONVERSION INFORMATION |
| | (NAVD 88 AND NGVD 29). |
| | 10. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND |
| | STORMWATER ALONG ENTIRE PROJECT FRONTAGE. |
| | 11. PLEASE ADD NOTE TO PLANS SPECIFYING CITY?S |
| | DOWNSTREAM LIFT STATION NUMBER. |
| | 12. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND |
| | IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED |
| | AREAS. |
| | 13. PROVIDE ONSITE CLEANOUTS NEAR PROPERTY LINE FOR |
| | PROPOSED SANITARY LATERALS. |
| | 14. PLEASE LABEL WATER LINES AS PRIVATE WHERE |
| | APPLICABLE. |
| | 15. PLEASE PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED |
| | LOCATION OF WATER METER AND BACKFLOW PREVENTION. |
| | 16. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE |
| | SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING |
| | PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT |
| | HIM AT 561-494-2262 OR [email protected] |
| | 17. PROVIDE DEDICATED UTILITY EASEMENTS TO ALLOW ACCESS |
| | FOR CITY PERSONNEL TO PROPOSED UTILITY WATER METERS. |
| | |
| | FOLLOWING COMMENTS FROM MARK HURLEY, FIELD CUSTOMER |
| | SERVICE SUPERVISOR, CITY OF WEST PALM BEACH PUBLIC |
| | UTILITIES, 561-822-2262 [email protected] |
| | |
| | BANYAN VIEW: |
| | |
| | -LANDSCAPE PLAN DOES NOT APPEAR TO BE DESIGNED WITH |
| | REGARD TO WATER METER AND BACKFLOW ASSEMBLY LAYOUT. |
| | SHOWS THEM POSITIONED DIFFERENTLY. PLEASE MAKE SURE |
| | LANDSCAPE PLANS SHOWS THEIR POSITIONING ACCURATELY, AND |
| | LANDSCAPING AND WATER UTILITIES DO NOT CONFLICT. |
| | |
| | -WATER PLAN SHOWS UTILITY MARKED IRR RUNNING ACROSS THE |
| | SOUTHEAST AREA OF THE PROPERTY, AND THEN UP AND ACROSS |
| | THE ROAD. PLEASE VERIFY THAT IT IS ACCURATELY SHOWN AND |
| | PRIVATELY OWNED. |
| | |
| | -ON WATER PLAN THERE IS A SMALL SYMBOL THAT LOOKS LIKE |
| | A BOX WITH A ?T? IN IT IN THE MIDDLE OF THE SIDEWALK |
| | NEAR THE STREET CROSSING. PLEASE IDENTIFY WHAT IT IS. |
| | |
| | -CIVIL PLANS ARE NOT ACCURATELY SHOWING THE EXISTING |
| | WATER METER BOX IN THE SIDEWALK JUST A FEW FEET WEST OF |
| | THE EXISTING DRIVEWAY. PLEASE SHOW AND ADD LABEL METER |
| | BOX AND WATER SERVICE WITH WHAT IS HAPPENING TO THEM. |
| | IT APPEARS THE CURRENT ACCOUNT HOLDER IS BANYAN CAY |
| | GOLF CLUB LLC. |
| | |
| | -CANNOT FIND PROPERTY ADDRESS ON CIVIL PLANS. |
| | |
| | |
| | BANYAN CAY RESIDENTIAL AREA: |
| | |
| | -THERE IS STILL A WATER SERVICE ISSUE THAT I DO NOT |
| | BELIEVE HAS BEEN RESOLVED WITH THE ISLAND AT THE |
| | ROUNDABOUT OF BANYAN CAY DRIVE. PLEASE PROVIDE CONTACT |
| | INFORMATION FOR PERSONS WITH KNOWLEDGE OF CONSTRUCTION |
| | AND RESPONSIBLE FOR THE LANDSCAPE ISLAND. |
| | |
| | |
| | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| | CONCERNS, THANKS. |
| | |
| | RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING |
| | SERVICES, (561) 494-1098, CELL (561) 246-9525 |
| | EMAIL: [email protected] |
| | WWW.WPB.ORG/ENGINEERING |
| | |
| |