Plan Review Notes
Plan Review Notes For Project Z20050013
Project Number Z20050013
Review Stop STORM
Sequence Number 3
Notes
Date Text
2021-04-08 10:27:32A NEW SITE PLAN IS BEING PRESENTED FOR THIS
 DEVELOPMENT. THIS IS A CONCEPTUAL LEVEL REVIEW.
 CONSTRUCTION LEVEL DETAILS, DESIGN CALCULATIONS AND THE
 POLLUTION PREVENTION PLAN WILL BE REVIEWED AS PART OF
 THE ENGINEERING DEVELOPMENT APPROVAL AND BUILDING
 PERMIT APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. LIMITED DESIGN INFORMATION IS PROVIDED ON THE
 CONCEPTUAL ENGINEERING PLANS.
  
 2. CAN THE PROPOSED 2? HIGH RETAINING WALL AT THE SW
 CORNER OF THE SITE BE LOCATED OUTSIDE THE 20? DRAINAGE
 EASEMENT?
  
 3. UPDATE THE UTILITIES SHOWN ON THE LANDSCAPE PLANS.
  
 4. ON THE ENGINEERING PLANS USE THE NAVD-NGVD
 CONVERSION FACTOR PROVIDED ON THE SURVEY.
  
 5. PROVIDE A SWALE BETWEEN THE EAST PROPERTY LINE AND
 THE BACK OF CURB TO PREVENT DIRECT STORMWATER RUNOFF
 FROM THE PROPERTY. ALSO SHOW A SWALE BETWEEN THE FRONT
 OF SIDEWALK AND EDGE OF PAVEMENT OF PRESIDENTIAL WAY.
 SHOW THE SWALES ON TYPICAL SECTION A-A.
  
 6. WHY IS THE SIDEWALK ALONG PRESIDENTIAL WAY BEING
 RELOCATED?
  
 7. PRESIDENTIAL WAY IS A PRIVATE ROAD, OWNED BY
 PRESIDENTIAL WAY ASSN INC. ACCORDING TO THE COUNTY
 PROPERTY APPRAISER?S WEBSITE. PERMISSION MAY BE NEEDED
 FROM THE OWNER FOR WORK WITHIN THE ROADWAY PARCEL.
  
 8. THE OVERALL MASTER DRAINAGE SYSTEM IS MAINTAINED BY
 BANYAN CAY DEVELOPMENT LLC ACCORDING TO SFWMD PERMIT
 50-07830-P (APPL. 161104-19). PROVIDE A LETTER FROM THE
 ENTITY INDICATING ITS ACCEPTANCE OF THE STORMWATER
 RUNOFF FROM THIS PROJECT INTO THE MASTER DRAINAGE
 SYSTEM.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. PROVIDE A COPY OF THE SFWMD ERP MODIFICATION WITH
 THE ENGINEERING PERMIT APPLICATION.
  
 3. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 4. DRAINAGE CALCULATIONS WILL BE REVIEWED WITH THE
 ENGINEERING PERMIT APPLICATION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  