Plan Review Notes
Plan Review Notes For Project Z20040015
Project Number Z20040015
Review Stop STORM
Sequence Number 3
Notes
Date Text
2021-09-27 16:53:58THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 9-8-2021 SUBMITTAL PACKAGE.
  
 1. WHAT IS THE VERTICAL CLEARANCE BETWEEN THE 15" STORM
 OUTFALL PIPE AND 8" ROOF DRAIN PIPE AS THEY CROSS THE
 6" WASTEWATER LINE, 4" FIRE LINE AND 1" WATER LINE.
 LABEL THESE VERTICAL CLEARANCES ON THE UTILITY PLAN AND
 UTILITY CONNECTION PROFILE ON SHEET C-11.
  
 2. NORTH ARROW POINTING TO THE WEST ON SHEET C-11.
  
 3. SITE LIGHT FIXTURE IS LOCATED WITHIN THE 2-FOOT
 OVERHANG OF THE PARKING STALLS ON THE WEST SIDE OF THE
 SITE.
  
 4. WHEEL STOPS MAY NOT BE NEEDED IF THERE IS TYPE 'D'
 CURB AT THE END OF THE PARKING STALL AND THE PARKING
 STALL INCLUDES 2 FEET OF OVERHANG OVER THE SIDEWALK OF
 LANDSCAPE STRIP. IF WHEEL STOPS ARE USED MAKE SURE THE
 PARKING SPACES ARE DEEP ENOUGH SO THAT THE STANDARD CAR
 DOES NOT STICK OUT INTO THE DRIVE LANE.
  
 5. CHECK COVER DEPTH OVER THE PROPOSED STORM PIPES IN
 THE PARKING LOT.
  
 6. CHECK THE THICKNESS OF THE CONCRETE ABOVE THE WEIR
 OPENING IN THE CONTROL STRUCTURE. IS THE GRATE
 SUPPORTED ON THIS SIDE?
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  