| 2020-05-07 12:16:10 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. 45TH ST. IS MAINTAINED BY PALM BEACH COUNTY AND |
| | MILITARY TRAIL IS MAINTAINED BY FDOT. APPROVALS FROM |
| | THESE AGENCIES WILL BE NEEDED BEFORE AN ENGINEERING |
| | PERMIT WILL BE ISSUED. |
| | |
| | 2. CHECK WITH PALM BEACH COUNTY WHETHER THEY PREFER THE |
| | SIDEWALK ALONG 45TH ST TO BE CONSTRUCTED AT BACK OF |
| | CURB OR AT THE FUTURE RIGHT-OF-WAY LINE. |
| | |
| | 3. CONSIDER REDUCING THE PARKING STALL DEPTHS BY TWO |
| | FEET AND PROVIDE 2 FEET OF OVERHANG IN ADDITIONAL |
| | LANDSCAPE WIDTH. |
| | |
| | 4. PROVIDE APPROVAL/ACCEPTANCE FROM FPL, FPUC AND ANY |
| | OTHER UTILITY WITH INTERESTS IN THE |
| | EASEMENTS/RIGHT-OF-WAY ALONG THE NORTHWEST CORNER OF |
| | THE SITE WHERE THE DETENTION AREA IS PROPOSED. |
| | |
| | 5. REMOVE EXISTING DRIVEWAY ACCESS POINTS THAT WILL NOT |
| | BE NEEDED AND RESTORE STANDARD SIDEWALK AND CURB AND |
| | GUTTER. |
| | |
| | 6. LANDSCAPING PLANS SHOW LANDSCAPING WITHIN THE FUTURE |
| | RIGHT OF WAY OF 45TH STREET. |
| | . |
| | 7. DRAINAGE SYSTEM TO MEET SFWMD ERP CRITERIA. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING |
| | CONSTRUCTION. |
| | |
| | 4. SITE IS WITHIN THE JURISDICTIONAL LIMITS OF NPBCID |
| | AND AN APPROVAL LETTER FROM NPBCID WILL BE NEEDED PRIOR |
| | TO STARTING CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 (O) |
| | 561-351-0510 (M) |
| | [email protected] |
| | |
| |