| 2021-02-04 11:35:11 | 1. CONFIRM THAT A COMPLETED LOS ANALYSIS SUMMARY TABLE |
| | HAS BEEN SUBMITTED DIRECTLY TO ENGINEERING (SHEET 33 OF |
| | CITY OF WPB DEVELOPMENT APPLICATION). |
| | 2. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY |
| | SEWER ARE REQUIRED. |
| | 3. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND |
| | IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED |
| | AREAS. |
| | 4. FOR FORMAL ENGINEERING SUBMITTAL , CUT AND CAP |
| | UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY |
| | LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY. |
| | 5. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE CALLOUT |
| | DOMESTIC BACKFLOW PREVENTER AS RPPA AND FIRE BACKFLOW |
| | PREVENTER AS DCDA. SPECIFY LEAD FREE DESIGN ON ALL |
| | BACKFLOWS. |
| | 6. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND |
| | NPDES NOI REQUIREMENTS WILL BE ENFORCED. |
| | - AN NOI IS REQUIRED FOR PROJECTS THAT: |
| | - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS |
| | THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF |
| | DEVELOPMENT OR SALE; |
| | - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE |
| | STATE OR TO SURFACE WATERS OF THE STATE THROUGH A |
| | MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4). |
| | - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF |
| | CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION |
| | THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL |
| | SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT |
| | OF THE 10-2 CERTIFICATION. |
| | 7. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES |
| | OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS. |
| | 8. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING |
| | APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT |
| | SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING |
| | SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED |
| | LEAD-FREE DESIGN. |
| | 9. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD |
| | RIGHT OF WAY. |
| | 10. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES |
| | ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY |
| | LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT |
| | PARCELS. |
| | 11. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES |
| | ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL |
| | ADDRESSES. |
| | 12. FOR FORMAL ENGINEERING SUBMITTAL, WHEN TRENCHING IN |
| | IN CITY MAINTAINED ROADWAY AREAS ADD NOTE TO PROVIDE 50 |
| | FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF |
| | PROPOSED TRENCH PER CITY OF WPB STANDARD DETAIL GC-4 |
| | AND 8. |
| | 13. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND |
| | INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER |
| | (Z-XXXXXXXX). |
| | |
| | |
| | THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD |
| | CUSTOMER SERVICE SUPERVISOR, WPB PUBLIC UTILITIES, |
| | PLEASE CONTACT 561-494-2262 OR [email protected]: |
| | |
| | -PLEASE VERIFY BUILDINGS WILL HAVE NO FIRE SPRINKLERS. |
| | -PLEASE ADD ARROWS ON FM & S.S. MAIN SHOWING DIRECTION |
| | OF FLOW ON UTILITY PLAN. |
| | -FOR FORMAL ENGINEERING SUBMITTAL: ADD RP TO UTILITY |
| | PLAN LABELS FOR BACKFLOW ASSEMBLIES, LABEL WATER |
| | SERVICE PIPE SIZE AND MATERIAL TYPE IN DETAILS A & B & |
| | C, AND ADD INFORMATION FOR CROSSING OF 6INCH CAS WM & |
| | 8INCH PVC S.S. |
| | |
| | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| | CONCERNS, THANKS. |
| | RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES |
| | DEPARTMENT |
| | DIRECT: (561) 494-1098 [email protected] |
| | |
| | |
| |