2020-09-25 18:08:26THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 9/23/20 SUBMITTAL SET OF PLANS:
  
 1. INDICATE THE BACK OF SIDEWALK AT THE DRIVEWAY WILL
 BE THE HIGH POINT FOR DRAINAGE BY ADDING FLOW ARROWS
 FOR SURFACE DRAINAGE.
  
 2. DRIVE LANE PARALLEL TO N. AUSTRALIAN AVE IS SHOWN AS
 TWO LANES IN THE SAME DIRECTION.
  
 3. WHAT TRAFFIC CONTROL WILL THERE BE FOR THE
 INTERSECTION OF THE WEST AND NORTH DRIVE LANES AT THE
 DRIVEWAY ENTRANCE? HOW WILL THE TWO NORTH BOUND LANES
 OPERATE?
  
 4. PERIMETER BERM AND/OR SWALE MAY BE REQUIRED ALONG
 THE EAST PROPERTY LINE.
  
 5. ENDWALL MAY BE REQIURED FOR PIPE IN CANAL R/W.
  
 6. TYPICAL SECTIONS BETWEEN PROPERTY LINE AND FACE OF
 BUILDING AT ALL PROPERTY LINES WILL BE REQUIRED FOR THE
 ENGINEERING PERMIT SUBMITTAL.
  
 TRACY WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]