| 2020-04-08 18:41:01 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | |
| | 1. LOCATE THE TOP OF BANK, WATER?S EDGE AND TOE OF |
| | SLOPE OF THE CANAL WHERE THE STORMWATER OUTFALL PIPE |
| | WILL BE LOCATED. |
| | |
| | 2. IDENTIFY THE VERTICAL DATUM ON THE ENGINEERING PLANS |
| | AND PROVIDE THE CONVERSION EQUATION TO NGVD 1929 IF |
| | NGVD 1929 IS NOT THE VERTICAL DATUM. LIST BOTH ON EVERY |
| | SHEET WITH ELEVATION INFORMATION. |
| | |
| | 3. PROVIDE THE VERTICAL DATUM CONVERSION EQUATION TO |
| | NGVD 1929 ON THE SURVEY. |
| | |
| | 4. AUSTRALIAN AVE IS MAINTAINED BY PALM BEACH COUNTY. |
| | APPROVAL FROM THE COUNTY IS REQUIRED FOR ANY |
| | IMPROVEMENTS WITHIN AUSTRALIAN AVE RIGHT OF WAY. |
| | |
| | 5. CONSIDER REDUCING THE DEPTH OF PARKING SPACES AND |
| | PROVIDE 2 FEET OF LANDSCAPE AREA OVERHANG. |
| | |
| | 6. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING |
| | CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |