| 2020-04-07 13:45:34 | 1. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY |
| | OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC |
| | RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF |
| | YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE |
| | MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL |
| | IN THE WPB ENGINEERING SERVICES DEPARTMENT AT |
| | [email protected] OR 561-494-1079 FOR FURTHER |
| | ASSISTANCE. NOTE THAT FIELD RECORDS ARE FOR INFORMATION |
| | ONLY. FIELD VERIFY UTILITY LOCATIONS USING FIELD |
| | SURVEY, POT-HOLING, SOFT DIGS ETC. |
| | 2. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH |
| | CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED, |
| | STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR |
| | MORE INFORMATION, REFER TO THE LINK BELOW: |
| | HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI |
| | CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL |
| | 3. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS |
| | OF ALL WATER, STORM WATER, AND SANITARY AND SEWER |
| | LINES, INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER |
| | AND SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES, |
| | METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE |
| | SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING |
| | GRADES, PIPES SIZES, MATERIALS, ELEVATIONS, |
| | ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL |
| | INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER |
| | LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE |
| | PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN |
| | VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. |
| | ADDITIONALLY, PLAN VIEW SHALL SHOW ALL EXISTING AND |
| | PROPOSED UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER |
| | OPTIC, ELECTRIC, GAS, AND CABLEVISION & |
| | TELECOMMUNICATION FACILITIES LOCATED ON THE |
| | RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL |
| | UTILITY CROSSINGS. CUT AND CAP UTILITIES NOT IN USE, |
| | AND REMOVE ANY ABANDONED UTILITY LINES LARGER THAN 2 |
| | INCHES FROM CITY RIGHT OF WAY. |
| | 4. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE |
| | DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB |
| | DEVELOPMENT APPLICATION). |
| | 5. SHOW DIMENSIONS OF PROPOSED DUMPSTER ENCLOSURE PER |
| | CURRENT CITY OF WPB STANDARD DETAIL GC-8. |
| | 6. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY |
| | SEWER ARE REQUIRED. |
| | 7. PLEASE CALLOUT DOMESTIC BACKFLOW PREVENTER AS RPPA |
| | AND FIRE BACKFLOW PREVENTER AS DCDA. |
| | 8. PROVIDE VERTICAL DATUM AND DATUM CONVERSION |
| | INFORMATION (NAVD 1988 AND NGVD 1929). |
| | 9. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND |
| | PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM |
| | AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE |
| | PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 FOR WATER. |
| | 10. COMMENT RESCINDED. |
| | 11. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE |
| | EASEMENT FOR PLACEMENT OF PROPOSED WATER METERS. |
| | 12. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE |
| | ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER |
| | METER AND BACKFLOW PREVENTION. |
| | 13. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES |
| | OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS. |
| | 14. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING |
| | APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT |
| | SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING |
| | SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED |
| | LEAD-FREE DESIGN. |
| | 15. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD |
| | RIGHT OF WAY. |
| | 16. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY |
| | ELEVATIONS AT MANHOLE TIE-IN. |
| | 17. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY MAINS |
| | ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY |
| | LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT |
| | PARCELS. |
| | 18. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER MAINS |
| | ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL |
| | ADDRESSES. |
| | 19. FOR FORMAL ENGINEERING SUBMITTAL, ADD NOTE TO |
| | PROVIDE 50 FT. PAVEMENT RESTORATION TRANSITION ON EACH |
| | SIDE OF PROPOSED TRENCH IN CITY MAINTAINED ROADWAY |
| | AREAS PER CITY OF WPB STANDARD DETAIL GC-9. |
| | 20. PLEASE NOTE THAT A PRE-PPRC-SUBMITTAL MEETING WITH |
| | ENGINEERING SERVICES IS HIGHLY SUGGESTED. |
| | 21. PLEASE RESPOND TO ALL COMMENTS IN WRITING. |
| | |
| | THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD |
| | CUSTOMER SERVICE SUPERVISOR |
| | CITY OF WEST PALM BEACH PUBLIC UTILITIES, 561-822-2262 |
| | [email protected] |
| | |
| | -SEE WELL ON PLAN, BUT RECORDS SHOW THAT THERE IS A |
| | DEDICATED IRRIGATION SERVICE THAT IS NOT CURRENTLY |
| | BEING USED. IS THE WELL BEING USED FOR IRRIGATION? |
| | -ARE ALL BACKFLOW PREVENTERS INCLUDING THE EXISTING 8 |
| | IN. DCDA FIRELINE BACKFLOW ASSEMBLY SHOWN ON THE SITE |
| | PLAN? |
| | -NEED SUBMIT UTILITY PLAN. |
| | |
| | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| | CONCERNS, THANKS. |
| | |
| | RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES |
| | DEPARTMENT |
| | 401 CLEMATIS STREET, 4TH FLOOR, WEST PALM BEACH, FL |
| | 33401 |
| | (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| | DIRECT: (561) 494-1098 |
| | MOBILE: (561) 246-9525 |
| | FAX: (561) 494-1116 |
| | EMAIL: [email protected] |
| | WWW.WPB.ORG/ENGINEERING |
| | |
| | |
| |