Plan Review Notes
Plan Review Notes For Project Z20020015
Project Number Z20020015
Review Stop STORM
Sequence Number 3
Notes
Date Text
2020-12-11 06:42:24THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 10/29/20 ROUTED SUBMITTAL PACKAGE. COMMENTS #1 THROUGH
 #5 CAN BE ADDRESSED THROUGH ENGINEERING PERMIT
 SUBMITTAL.
  
 1. ADD A SCALE BAR TO ALL PLAN SHEETS TO FACILITATE
 SCALING THE PDF COPIES ON THE COMPUTER.
  
 2. STRIPING LAYOUT SHOWN ON THE PROPOSED PARKING DETAIL
 ON SHEET C-2.2 DOES NOT MEET THE CITY'S DETAIL FOUND IN
 THE CODE OF ORDINANCES. THE VERTICAL 4-INCH STRIPES
 SHOULD BE SPACED 12 INCHES APART (16 INCHES FROM CENTER
 OF STRIPE TO CENTER OF STRIPE) AND THE ENDS OF THE
 STRIPES ARE CONNECTED WITH A 4-INCH HORIZONTAL STRIPE.
  
 3. STRUCTURE S-3 IS LISTED WITH THREE INVERTS (NE, S
 AND W) IN THE DRAINAGE STRUCTURE TABLE BUT THE PLAN
 VIEW ONLY SHOWS TWO PIPES (E AND S) CONNECTED TO THE
 STRUCTURE. VERIFY ALL OF THE OTHER STRUCTURES' INVERTS
 ARE CORRECT.
  
 4. PROVIDE SUMP PER CITY'S DETAIL FOR STRUCTURE S-19 IN
 THE R/W OF 25TH STREET.
  
 5. INDICATE IF THE DRIVE LANES NORTH AND SOUTH OF THE
 BUILDING WILL BE INVERTED CROWN OR SHED SECTION.
  
 6. SHOULD THE STOP BAR FOR THE DRIVE THRU LANES BE
 MOVED FURTHER WEST? THE BUILDING WILL BE IN THE SIGHT
 TRIANGLE.
  
 7. WHO/WHAT IS THE 10' ACCESS EASEMENT ALONG THE NORTH
 SIDE OF THE SITE FOR? THE TRANSFORMER AND DUMPSTER ARE
 LOCATED WITHIN THE EASEMENT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  