Plan Review Notes
Plan Review Notes For Project Z20020015
Project Number Z20020015
Review Stop STORM
Sequence Number 2
Notes
Date Text
2020-09-21 14:40:39THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 8/24/20 SUBMITTAL PACKAGE:
  
 1. LIST THE VERTICAL DATUM AND CONVERSION EQUATION TO
 NGVD1929 ON ALL SHEETS WITH ELEVATION INFORMATION
 (SURVEY, SHEETS C-1.0, C-2.0, C-3.1, C-4.0, ETC.)
  
 2. ON SHEET C-1.0 DEMO. PLAN, REMOVE THE EXISTING STORM
 PIPE ALL THE WAY TO THE CATCH BASIN ON THE NORTH SIDE
 OF 25TH ST.
  
 3. CONSIDER BREAKING UP THE EXFILTRATION TRENCH BETWEEN
 STRUCTURES S-9 AND S-10 TO ALLOW THE WATER SERVICE AND
 SEWER LATERALS TO CROSS OVER THE STORM PIPE OUTSIDE OF
 THE EXFILTRATION TRENCH. EXTEND THE EXFILTRATTION
 TRENCH BETWEEN STRUCTURES S-14 AND CS OR ADD
 EXFILTRATION TRENCH BETWEEN STRUCTURES S-6 AND S-7.
  
 4. IN THE DRAINAGE STRUCTURE SCHEDULE ON SHEET C-3.0,
 ALL STRUCTURES ARE LISTED AS CATCH BASINS.
  
 5. CONTROL STRUCTURES (WEIRS) USED TO SURCHARGE THE
 EXFILTRATION TRENCHES CANNOT INCLUDE A BLEEDER.
  
 6. THE WEIR ELEVATION FOR STRUCTURE CS IS LISTED AS
 10.00 IN THE DRAINAGE STRUCTURE SCHEDULE TABLE BUT THE
 TOP OF TRENCH ELEVATION IS SHOWN AS 11.50.
  
 7. USE THE LOWEST CATCH BASIN ELEVATON IN THE
 EXFILTRATION TRENCH LONGITUDINAL SECTION DETAIL ON
 SHEET C-3.1.
  
 8. ADD A DRAINAGE CATCH BASIN IN THE SWALE ON THE EAST
 SIDE OF THE DRIVEWAY ON 25TH ST AND PIPE TO THE
 EXISTING CATCH BASIN AT THE CORNER OF N. AUSTRALIAN
 AVE/25TH ST.
  
 9. PROVIDE TYPICAL CROSS SECTIONS FOR ALL FOUR SIDES OF
 THE PROPERTY, EXTENDING FROM THE CENTERLINE OF THE ROAD
 RIGHT OF WAY AND CANAL RIGHT OF WAY AND THE NORTH
 PROPERTY LINE TO INTERIOR POINTS OF THE PAVED AREA.
  
 10. EXPLAIN WHAT THE TOE OF BANK REPRESENTS FOR THE
 CANAL. THE WATER TABLE IS SHOWN TO BE AT ELEVATION 8
 FEET NAVD AND THERE ARE SPOT GRADES BETWEEN 7.8 AND
 11.4 ALONG THIS TOE OF BANK LINE.
  
 11. LANDSCAPE PLANS SHOW SEVERAL TREES NEAR OR OVER THE
 PROPOSED EXFILTRATION TRENCHES AND SEWER LATERALS.
  
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120