| Date |
Text |
| 2021-05-19 10:42:33 | CONDITIONS OF APPROVAL (OVERALL - UPDATED 5/19/2021): |
| | |
| | 1.) A RIGHT-OF-WAY PERMIT FOR THE MODIFICATIONS TO THE |
| | ACCESS POINT(S) ON SOUTH DIXIE HIGHWAY SHALL BE |
| | RECEIVED FROM THE FLORIDA DEPARTMENT OF TRANSPORTATION |
| | (FDOT) PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR |
| | ANY EXTERIOR SITE WORK TO BE COMPLETED FOR THE PROJECT. |
| | A COPY OF THE REQUIRED FDOT PERMIT SHALL BE PROVIDED TO |
| | THE DEVELOPMENT SERVICES DEPARTMENT - PLANNING DIVISION |
| | UPON RECEIPT OF THE PERMIT. |
| | |
| | 2.) HE BICYCLE RACKS SHALL BE ORIENTATED PARALLEL (NOT |
| | PERPENDICULAR AS PROVIDED IN THE PLANS) TO SOUTH DIXIE |
| | HIGHWAY, AS IT WOULD BE MORE FUNCTIONAL WITH THE DESIGN |
| | AND PLACEMENT OF THE BICYCLE RACK PAD ON SITE. THE |
| | DESIGN OF THE BICYCLE RACK PAD SHALL REMAIN CONSISTENT |
| | WITH THE CITY'S BICYCLE PARKING GUIDELINES. A SEPARATE |
| | BUILDING PERMIT WILL BE REQUIRED FOR THE INSTALLATION |
| | OF THE BICYCLE RACK(S) AND PAD. |
| | |
| | 3.) RIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY |
| | (C.O.) FOR THE PROJECT, THE APPLICANT SHALL COMPLETE |
| | THE FOLLOWING: A.) A UNITY OF TITLE APPLICATION SHALL |
| | BE FILED WITH THE ENGINEERING SERVICES DEPARTMENT, AND |
| | A COPY OF THE RECORDED UNITY OF TITLE DOCUMENT SHALL BE |
| | SUBMITTED AND FILED WITH THE DEVELOPMENT SERVICES |
| | DEPARTMENT - PLANNING DIVISION. B.) GRANT OF UTILITY |
| | EASEMENTS ALONG THE SOUTH AND WEST PROPERTY LINES AND |
| | ANY REQUIRED FOR METER. C.) UPDATE TRAFFIC STUDY |
| | SHOWCASING DRIVEWAY VOLUMES ON DIXIE HIGHWAY. D.) |
| | ANALYZE THE FOLLOWING INTERSECTIONS, UNDER THE SOUTH |
| | DIXIE LANE ELIMINATION PROJECT SCENARIO: I) SOUTH DIXIE |
| | HIGHWAY AND BELVEDERE ROAD II) SOUTH DIXIE HIGHWAY AND |
| | VALENCIA ROAD |
| | |
| | 4.) PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON |
| | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE |
| | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT |
| | SERVICES DEPARTMENT - PLANNING DIVISION. |
| | |
| | |
| | ********* |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| 2021-05-04 08:52:13 | PLEASE ADDRESS THE FOLLOWING IN THE SITE PLAN AND SITE |
| | PLAN DETAIL SHEETS FOR FINAL SITE PLAN APPROVAL WITH |
| | ZONING: |
| | |
| | 1.) THE PARKING STALL STRIPING DETAIL AND SITE PLAN |
| | SHOWS THE PARKING STALLS ENCROACHING INTO THE DRIVE |
| | AISLE. PLEASE CORRECT. |
| | |
| | |
| | CONDITIONS OF APPROVAL FOR ZONING: |
| | |
| | 1.) A RIGHT-OF-WAY PERMIT FOR THE MODIFICATIONS TO THE |
| | ACCESS POINT(S) ON SOUTH DIXIE HIGHWAY SHALL BE |
| | RECEIVED FROM THE FLORIDA DEPARTMENT OF TRANSPORTATION |
| | (FDOT) PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR |
| | ANY EXTERIOR SITE WORK TO BE COMPLETED FOR THE PROJECT. |
| | A COPY OF THE REQUIRED FDOT PERMIT SHALL BE PROVIDED TO |
| | THE DEVELOPMENT SERVICES DEPARTMENT - PLANNING DIVISION |
| | UPON RECEIPT OF THE PERMIT. |
| | |
| | 2.) THE BICYCLE RACKS SHALL BE ORIENTATED PARALLEL (NOT |
| | PERPENDICULAR AS PROVIDED IN THE PLANS) TO SOUTH DIXIE |
| | HIGHWAY, AS IT WOULD BE MORE FUNCTIONAL WITH THE DESIGN |
| | AND PLACEMENT OF THE BICYCLE RACK PAD ON SITE. THE |
| | DESIGN OF THE BICYCLE RACK PAD SHALL REMAIN CONSISTENT |
| | WITH THE CITY'S BICYCLE PARKING GUIDELINES. A SEPARATE |
| | BUILDING PERMIT WILL BE REQUIRED FOR THE INSTALLATION |
| | OF THE BICYCLE RACK AND PAD. |
| | |
| | |
| | |
| |