| 2020-03-12 11:47:30 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE ENGINEERING AND LANDSCAPE PLANS DO NOT MATCH THE |
| | SITE PLAN. |
| | |
| | 2. ADD FLOW ARROWS TO THE ENGINEERING PLAN TO SHOW |
| | SURFACE WATER RUNOFF DIRECTION. |
| | |
| | 3. AVOID PUTTING UTILITIES UNDER LANDSCAPE ISLANDS. |
| | |
| | 4. CONSIDER CREATING 2 FOOT OVERHANGS INTO LANDSCAPE |
| | AREAS FOR PARKING SPACES. |
| | |
| | 5. CATCH BASIN GRATE ELEVATIONS APPEAR TO BE HIGHER |
| | THAN SOME ADJACENT PARKING LOT GRADES. |
| | |
| | 6. THE TRAVEL LANE SPACE BETWEEN THE LANDSCAPE ISLANDS |
| | ON THE ENGINEERING PLAN APPEARS TO NARROW FOR TWO WAY |
| | TRAFFIC. |
| | |
| | 7. PROVIDE BOTTOM ELEVATION OF EXISTING ONSITE DRAINAGE |
| | STRUCTURES THAT ARE TO REMAIN. |
| | |
| | 8. CURBING NEEDED FOR NARROW PARKING AREAS NORTH OF THE |
| | LANDSCAPE ISLANDS. |
| | |
| | 9. SHOW UTILITIES ON THE LANDSCAPE PLAN. |
| | |
| | 10. SCALES SHOULD MATCH FOR SURVEY, ENGINEERING PLANS |
| | AND LANDSCAPE PLANS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING |
| | CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |
Print |