| 2020-02-10 17:29:52 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE OBTAINED FROM THE |
| | ENGINEERING SERVICES DEPARTMENT. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. SITE PLANS DIFFER ON ENGINEERING PLAN AND LANDSCAPE |
| | PLAN. |
| | |
| | 2. SHOW UTILITIES ON THE LANDSCAPE PLAN. |
| | |
| | 3. PROVIDE CROSS SECTIONS FOR ALL FOUR SIDES OF THE |
| | PROPERTY SHOWING HOW SITE WILL BE GRADED ALONG THE |
| | PROPERTY LINE. THE CROSS SECTION FOR THE SOUTH PROPERTY |
| | LINE SHALL INCLUDE THE ALLEY RIGHT OF WAY. |
| | |
| | 4. NAVD1988 / NGVD1929 CONVERSION EQUATIONS DIFFER ON |
| | THE ENGINEERING PLAN AND SURVEY. |
| | |
| | 5. SHOW MILL AND RESURFACING LIMITS AND SIDEWALK |
| | REPLACEMENT LIMITS FOR UTILITY CUTS. |
| | |
| | 6. THE EXISTING DRAINAGE ON CLEMATIS ST. CONNECTS TO |
| | THE CURB INLET AT THE SE CORNER OF QUADRILLE PLAZA |
| | DRIVE AND CLEMATIS ST. |
| | |
| | 7. REVISE THE EXISTING DOUBLE PARALLEL LINES FOR THE |
| | STORM PIPES AS A SINGLE LINE ON THE ENGINEERING PLAN.. |
| | |
| | 8. REVISE THE EXISTING DOUBLE PARALLEL LINES FOR THE |
| | SANITARY SEWER MAIN IN THE ALLEY AS A SINGLE LINE ON |
| | THE ENGINEERING PLAN. |
| | |
| | 9. LABEL QUADRILLE PLACE BLVD. AS QUADRILLE PLAZA DRIVE |
| | ON THE ENGINEEERING PLAN, LANDSCAPE PLAN AND |
| | ARCHITECTURAL PLANS. |
| | |
| | 10. THE ALLEY SHALL BE GRADED TO DRAIN. |
| | |
| | 11. DRAINAGE SYSTEM SHALL BE DESIGNED TO PROVIDE WATER |
| | QUALITY TREATMENT AND PEAK FLOW ATTENUATION IN |
| | ACCORDANCE WITH SFWMD CRITERIA. |
| | |
| | 12. SHOW DRAINAGE FLOW ARROWS ON THE ENGINEERING PLAN. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE OBTAINED FROM THE ENGINEERING SERVICES |
| | DEPARTMENT. |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PERMIT, IF |
| | APPLICABLE, PRIOR TO STARTING CONSTRUCTION. |
| | |
| | TRACY WARD, PE |