2020-02-10 17:45:36THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE OBTAINED FROM THE
 ENGINEERING SERVICES DEPARTMENT.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. ALL PLANS AND SURVEYS SHOULD USE THE SAME VERTICAL
 DATUM. THE CITY'S VERTICAL DATUM IS NGVD 1929. THE CITY
 HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE
 CONVERSION EQUATION TO NGVD1929 IS PROVIDED. THE
 VERTICAL DATUM AND CONVERSION EQUATION TO NGVD1929
 SHOULD BE LISTED ON EVERY PLAN SHEET WITH ELEVATION
 INFORMATION.
  
 2. PIPE INVERTS FOR EXFILTRATION TRENCHES DO NOT AGREE
 WITH THE EXFILTRATION DETAIL.
  
 3. DRAINAGE STRUCTURE #4 WILL BE INSTALLED IN THE
 MIDDLE OF AN EXISTING EXFILTRATION TRENCH. PROVIDE
 PRB'S ON EACH CONNECTION TO THE EXILTRATION TRENCH.
  
 4. PROVIDE INFORMATION ON THE PLANS FOR THE EXISTING
 CONTROL STRUCTURE AND OUTFALL.
  
 5. SHOW MILL AND OVERLAY LIMITS FOR THE UTILITY CUTS.
  
 6. PROVIDE DOCUMENTATION OF A MASTER ASSOCIATION TO
 OPERATE AND MAINTAIN THE SURFACE WATER MANAGEMENT
 SYSTEM. DRAINAGE EASEMENTS IN FAVOR OF EACH PARCEL MAY
 BE REQUIRED.
  
 7. PART OF SITE FALLS WITHIN A SPECIAL FLOOD HAZARD
 AREA (SFHA). A MINIMUM OF 2 FEET OF FREEBOARD ABOVE THE
 BASE FLOOD ELEVATION IS REQUIRED FOR STRUCTURES ON
 PARCELS WITHIN A SFHA.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE OBTAINED FROM THE ENGINEERING SERVICES
 DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120