| 2020-06-30 08:33:57 | PASSED WITH PROVISOS: | | | | | | 1. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE | | | ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER | | | METER AND BACKFLOW PREVENTION. | | | 2. FOR FORMAL ENGINEERING SUBMITTAL, LABEL ALL CITY | | | OWNED UTILITIES PIPE SIZES AND MATERIALS IN RIGHT OF | | | WAY. | | | 3. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE ALL | | | RELEVANT CURRENT CITY OF WPB STANDARD DETAILS; ADD | | | PAVEMENT RESTORATION DETAIL GC-8 NOTE TO UTILITY | | | SHEETS. | | | | | | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR | | | CONCERNS, THANKS. | | | RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES | | | DEPARTMENT | | | DIRECT: (561) 494-1098 [email protected] | | | |
| |