| 2020-01-08 11:27:45 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTPS:/ |
| | /WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PE |
| | RMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE PROPOSED OUTFALL STORM PIPE TO CONNISTON ROAD IS |
| | SHOWN GOING NEXT TO AN EXISTING MAHOGANY TREE. WHAT |
| | IMPACT WILL CONSTRUCTION OF THIS PIPE HAVE ON THE TREE |
| | AND CAN THE IMPACT BE MITIGATED? |
| | |
| | 2. NO GRADING INFORMATION WAS PROVIDED. |
| | |
| | 3. MINIMIZE THE AMOUNT OF IMPERVIOUS AREA RUNOFF THAT |
| | WILL SHEET FLOW TOWARD THE RIGHT OF WAY AND ACROSS THE |
| | SIDEWALK. |
| | |
| | 4. PROVIDE CROSS SECTIONS FROM THE PROPERTY LINE TO THE |
| | BUILDING AND TO THE PARKING AREAS. PERIMETER BERMS |
| | SHOULD BE PROVIDED TO CONTAIN THE STORMWATER RUNOFF. |
| | |
| | 5. PROVIDE A CONDITION ASSESSMENT OF THE CATCH BASIN TO |
| | BE MODIFIED ON CONNISTON ROAD. |
| | |
| | 6. SOUTHERN BLVD. IS MAINTAINED BY FDOT. A PERMIT WILL |
| | BE NEEDED FROM FDOT FOR ANY WORK WITHIN THE SOUTHERN |
| | BLVD RIGHT OF WAY. |
| | |
| | 7. STORMWATER MANAGEMENT SYSTEM TO BE DESIGNED TO MEET |
| | SFWMD CRITERIA FOR WATER QUALITY TREATMENT AND PEAK |
| | FLOW ATTENUATION. |
| | |
| | 8. CONSIDER LOW IMPACT DEVELOPMENT (LID) BEST |
| | MANAGEMENT PRACTICES BESIDES EXFILTRATION TRENCHES FOR |
| | STORMWATER TREATMENT. CAN DEPRESSED STORMWATER |
| | DETENTION AREAS BE INCORPORATED IN THE LANDSCAPE GREEN |
| | SPACES AROUND THE BUILDING AND ALONG CONNISTON ROAD? |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PERMIT PRIOR TO |
| | STARTING CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| | |
| |