Plan Review Notes
Plan Review Notes For Project Z19120009
Project Number Z19120009
Review Stop STORM
Sequence Number 3
Notes
Date Text
2020-06-23 15:39:11THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 6/19/2020 CIVIL PLANS AND CAN BE ADDRESSED DURING
 ENGINEERING PERMIT SUBMITTAL.
  
 1. VERIFY THERE WILL BE SUFFICIENT VERTICAL CLEARANCE
 BETWEEN THE BOTTOM OF THE TOP SLAB OF THE CONTROL
 STRUCTURE MANHOLES AND THE TOP OF THE WEIRS. MANHOLES
 SHOULD BE FLUSH WITH THE SURROUNDING AREA.
  
 2. ALL OF THE DRAINAGE STRUCTURES ON THE NORTH SIDE OF
 BANYAN BLVD. SHOULD BE LABELED "... TO BE INSTALLED IN
 WPB PROJECT ...".
  
 3. LABEL THE PIPE SIZES, MATERIAL AND INVERTS OF THE
 STORM PIPES BETWEEN THE CONTROL STRUCTURES AND DRAINAGE
 STRUCTURES ON BANYAN BLVD. MINIMUM 15" RCP.
  
 4. PROVIDE THE DESIGN INFORMATION FOR THE STRUCTURES ON
 BANYAN BLVD. PROVIDE A REFERENCE TO WHERE THE
 INFORMATION CAME FROM.
  
 5. ON THE CROSS SECTIONS, SHOW THE LANDSCAPE AREAS WITH
 SWALE (DEPRESSION) SECTION. THE ONSITE AREAS SHOULD NOT
 DRAIN DIRECTLY TO ADJACENT PROPERTIES.
  
 6. THE PIPE FOR THE WEST EXFILTRATION TRENCH DOES NOT
 APPEAR TO BE CENTERED IN THE TRENCH. THE EXFILTRATION
 TRENCH IS TO BE COMPLETELY LOCATED WITHIN THE PROPERTY.
  
 7. PROVIDE DETAILS FOR EXFILTRATION TRENCH, PRB,
 CONTROL STRUCTURES, ETC.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120 (O)
 561-351-0510 (M)