2020-04-15 15:54:28THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 4/10/2020 SUBMITTAL PACKAGE.
  
 1. THIS REVIEW DOES NOT INCLUDE THE PROPOSED
 IMPROVEMENTS ON THE CRA PROPERTY. PROVIDE A SEPARATE
 SET OF PLANS.
  
 2. PROVDE A MAP LABELING THE PIPES AND STRUCTURE
 NUMBERS USED IN THE CCTV VIDEOS/REPORTS.
  
 3. THE DRAINAGE SYSTEM ON THE EAST SIDE OF THE PROPERTY
 IS PROPOSING TO CONNECT TO AN INLET THAT IS BEING
 INSTALLED AS PART OF THE BANYAN BLVD IMPROVEMENT
 PROJECT. IF THIS PROJECT DOES NOT PROCEED, YOU WILL
 NEED TO REVISE WHERE THE DRAINAGE SYSTEM WILL CONNECT
 TO THE MS4, WHICH MAY REQUIRE INSTALLING A MANHOLE
 DIRECTLY SOUTH ON THE STORM MAIN. CHANGE THE MANHOLE IN
 THE RIGHT OF WAY WITHIN THE BIKE LANE ON THE SOUTHEAST
 SIDE OF THE BUILDING TO A CATCH BASIN INLET TO BE
 LOCATED COMPLETELY OUTSIDE THE BIKE LAKE. ANY REASON
 WHY THIS CATCH BASIN INLET CANNOT CONNECT TO THE ONSITE
 MANHOLE INSTEAD OF THE ONSITE CATCH BASIN?
  
 4R. PROVIDE CROSS SECTIONS FOR ALL FOR SIDES OF THE
 BUILDING EXTENDING FROM THE FACE OF THE BUILDING TO
 ROADWAY CENTERLINES AND PROPERTY LINES. THERE SHOULD
 NOT BE FLOW ONTO ADJACENT PROPERTIES.
  
 5. ON THE SITE PLAN, SHEET SP-1, PROPERLY SHOW THE
 ALLEY AND 20 FT ROW NORTH OF THE SITE AS PRIVATE
 PARCELS.
  
 6. MOVE THE FH IN THE SOUTHWEST CORNER OF THE SITE INTO
 THE RIGHT-OF-WAY.
  
 TRACY WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved