| 2020-01-08 11:30:51 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT |
| | HTTPS://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FO |
| | RMS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. ALL PLANS AND SURVEYS SHOULD USE THE SAME VERTICAL |
| | DATUM. THE CITY'S VERTICAL DATUM IS NGVD 1929. THE CITY |
| | HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE |
| | CONVERSION EQUATION TO NGVD1929 IS PROVIDED. THE |
| | VERTICAL DATUM AND CONVERSION EQUATION TO NGVD1929 |
| | SHOULD BE LISTED ON EVERY PLAN SHEET WITH ELEVATION |
| | INFORMATION. |
| | |
| | 2. ROOF DRAINAGE NEEDS TO BE CONNECTED TO THE ONSITE |
| | STORMWATER MANAGEMENT SYSTEM. |
| | |
| | 3. CONSIDER OTHER LOW IMPACT DEVELOPMENT (LID) BEST |
| | MANAGEMENT PRACTICES BESIDES EXFILTRATION TRENCHES FOR |
| | STORMWATER TREATMENT. |
| | 4. STORMWATER MANAGEMENT SYSTEM TO BE DESIGNED TO MEET |
| | SFWMD CRITERIA FOR WATER QUALITY TREATMENT AND PEAK |
| | FLOW ATTENUATION. |
| | |
| | 5. SITE DATA ON SHEET C-1 DOES NOT MATCH WHAT IS LISTED |
| | ON SHEET SP-1. |
| | |
| | 6. ON SHEET C-1 IDENTIFY THROUGH HATCHING OR SHADING |
| | WHERE THE 29,318 S.F. OF PERVIOUS SPACE IS LOCATED ON |
| | THE 33,280 S.F PARCEL. |
| | |
| | 7. IT APPEARS THE DRIVEWAY ON BANYAN STREET MAY AFFECT |
| | A LIGHT POLE. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING |
| | CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| | |
| |