Plan Review Notes
Plan Review Notes For Project Z19120009
Project Number Z19120009
Review Stop STORM
Sequence Number 1
Notes
Date Text
2020-01-08 11:30:51THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTPS://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FO
 RMS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. ALL PLANS AND SURVEYS SHOULD USE THE SAME VERTICAL
 DATUM. THE CITY'S VERTICAL DATUM IS NGVD 1929. THE CITY
 HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE
 CONVERSION EQUATION TO NGVD1929 IS PROVIDED. THE
 VERTICAL DATUM AND CONVERSION EQUATION TO NGVD1929
 SHOULD BE LISTED ON EVERY PLAN SHEET WITH ELEVATION
 INFORMATION.
  
 2. ROOF DRAINAGE NEEDS TO BE CONNECTED TO THE ONSITE
 STORMWATER MANAGEMENT SYSTEM.
  
 3. CONSIDER OTHER LOW IMPACT DEVELOPMENT (LID) BEST
 MANAGEMENT PRACTICES BESIDES EXFILTRATION TRENCHES FOR
 STORMWATER TREATMENT.
 4. STORMWATER MANAGEMENT SYSTEM TO BE DESIGNED TO MEET
 SFWMD CRITERIA FOR WATER QUALITY TREATMENT AND PEAK
 FLOW ATTENUATION.
  
 5. SITE DATA ON SHEET C-1 DOES NOT MATCH WHAT IS LISTED
 ON SHEET SP-1.
  
 6. ON SHEET C-1 IDENTIFY THROUGH HATCHING OR SHADING
 WHERE THE 29,318 S.F. OF PERVIOUS SPACE IS LOCATED ON
 THE 33,280 S.F PARCEL.
  
 7. IT APPEARS THE DRIVEWAY ON BANYAN STREET MAY AFFECT
 A LIGHT POLE.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  