Plan Review Notes
Plan Review Notes For Project Z19090015
Project Number Z19090015
Review Stop ENG - PPRC
Sequence Number 3
Notes
Date Text
2020-01-15 11:51:42PASSED WITH PROVISOS:
  
 1. PLEASE UPDATE LOS ANALYSIS SUMMARY TABLE AND
 RESUBMIT DIRECTLY TO ENGINEERING.
 2. FOR FORMAL ENGINEERING SUBMITTAL , PROVIDE
 CALCULATIONS ON PLANS OF EXISTING AND PROPOSED DEMANDS
 FOR WATER & SEWER (AVERAGE, MAXIMUM AND PEAK) AND FIRE
 FLOW DEMANDS. CALCULATIONS SHALL BE PER FAC 64E-6 FOR
 SEWER AND PER FAC 64-E.008 FOR WATER.
 3. FOR FORMAL ENGINEERING SUBMITTAL , PLEASE PROVIDE
 CALCULATIONS OF REVISED PERVIOUS AND IMPERVIOUS
 CALCULATIONS FOR THE PROPOSED IMPACTED AREAS.
 4. FOR FORMAL ENGINEERING SUBMITTAL , COORDINATE WITH
 MARK HURLEY, FIELD CUSTOMER SERVICE SUPERVISOR WITH
 CITY OF WPB PUBLIC UTILITIES, REGARDING PLACEMENT OF
 BACKFLOW DEVICES AND WATER METERS. CONTACT HIM AT
 561-494-2262 OR [email protected]
 5. FOR FORMAL ENGINEERING SUBMITTAL , PLANS SHALL SHOW
 PROPOSED LOCATIONS AND DIMENSIONS OF ALL WATER,
 STORMWATER, AND SANITARY AND SEWER LINES, INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, METERS, AND
 OTHERS DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. ALL
 AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE VIEW.
 DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN
 VIEW FOR ALL SANITARY AND STORM SEWERS. ADDITIONALLY,
 PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED
 UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC,
 ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION
 FACILITIES LOCATED ON THE RIGHT-OF-WAY.
 6. FOR FORMAL ENGINEERING SUBMITTAL , CUT AND CAP
 UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY
 LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY.
 7. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER
 METER AND BACKFLOW PREVENTION.
 8. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE CALLOUT
 DOMESTIC BACKFLOW PREVENTER AS RPPA AND FIRE BACKFLOW
 PREVENTER AS DCDA. SPECIFY LEAD FREE DESIGN ON ALL
 BACKFLOWS.
 9. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES
 OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS.
 10. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 11. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD
 RIGHT OF WAY.
 12. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY
 ELEVATIONS AT MANHOLE TIE-IN.
 13. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES
 ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY
 LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT
 PARCELS.
 14. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES
 ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL
 ADDRESSES.
 15. FOR FORMAL ENGINEERING SUBMITTAL, WHEN TRENCHING IN
 IN CITY MAINTAINED ROADWAY AREAS ADD NOTE TO PROVIDE 50
 FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF
 PROPOSED TRENCH PER CITY OF WPB STANDARD DETAIL GC-9.
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
  
 RICK ROSSANO, PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098 [email protected]
  
  