Plan Review Notes
Plan Review Notes For Project Z19090015
Project Number Z19090015
Review Stop STORM
Sequence Number 1
Notes
Date Text
2019-10-08 16:52:40THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
 1. MIN. FFE IS TWO FEET ABOVE BASE FLOOD ELEVATION FOR
 STRUCTURES WITHIN SPECIAL FLOOD HAZARD AREAS.
  
 2. SHOW THE CHURCH'S STORMWATER OUTFALL PIPE (AND
 EASEMENT?) ON THE PLANS.
  
 3. SHOW AND LABEL PERIMETER BERM ALONG THE PROPERTY
 LINES. PROVIDE A DETAIL OF THE BERM.
  
 4. ADD SPOT GRADES AROUND THE BUILDINGS AND FOR THE
 SIDEWALKS BETWEEN THE BUILDINGS.
  
 5. CONSIDER REDUCING THE LENGTH OF THE PARKING SPACES,
 PROVIDE TWO FEET OF OVERHANG AND REPLACING THE WHEEL
 STOPS WITH CURBS.
  
 6. ON SECTION A-A (SHEET C-127), PROVIDE A 6 INCH DEEP
 SWALE ALONG THE BACK OF SIDEWALK WITH SLOPES 4:1 OR
 FLATTER.
  
 7. FLOATING TURBIDITY BARRIER WILL BE NEEDED IN THE
 LAKE TO CONTROL TURBIDITY DURING LAKE EXCAVATION.
  
 8. IDENTIFY WHERE THE EXISTING POND/WETLAND WILL BE
 RELOCATED TO WHEN THE LAKE IS EXPANDED.
  
 9. IDENTIFY WHO WILL BE RESPONSIBLE FOR THE 20' LAKE
 MAINTENANCE EASEMENT.
  
 10. ON SHEET C-121, THE GRADING PLAN SHOWS SPOT GRADES
 OF 14.65 ON THE DRIVEWAY AND FLOW ARROWS POINTING
 TOWARD ELEVATION 15.00.
  
 11. NUMBER THE DRAINAGE STRUCTURES FOR EASE OF
 REFERENCE. IDENTIFY THE CONTROL STRUCTURE.
  
 12. POLLUTANT RETARDANT BAFFLES (PRB'S) WILL BE NEEDED
 FOR ALL STRUCTURES CONNECTED TO EXFILTRATION TRENCHES.
  
 12. IT APPEARS THERE ARE CLEANOUTS AT ALL OF THE
 SANITARY SEWER LATERAL WYE CONNECTIONS TO THE SEWER
 MAIN.
  
 13. SHOW MILL AND RESURFACE LIMITS ON VILLAGE BLVD FOR
 THE UTILITY TRENCH CUTS.
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  