| Notes |
| Date |
Text |
| 2019-12-12 11:56:26 | THE FOLLOWING COMMENT IS FROM THE REVIEW OF THE | | | DECEMBER 5, 2019 REVIEW SUBMITTAL PACKAGE: | | | | | | 1. MAINTAIN THE MINIMUM PERIMETER ELEVATION (USE THE | | | HIGHER OF TWO PROPERTIES) FOR THE DRIVE CONNECTION TO | | | THE PROPERTY TO THE NORTH UNLESS BOTH PROPERTIES SHARE | | | THE SAME STORMWATER MANAGEMENT SYSTEM AND WATER LEVELS | | | ON BOTH SIDES OF THE PROPERTY LINE ARE CONTROLLED BY | | | THE SAME CONTROL STRUCTURE. | | | | | | TRACY WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | [email protected] | | | 561-494-1120 |
| |
Print |
|