Plan Review Notes
Plan Review Notes For Project Z19090009
Project Number Z19090009
Review Stop ENG - PPRC
Sequence Number 1
Notes
Date Text
2019-10-07 11:15:171. THE CITY OF WEST PALM BEACH HAS A NUMBER OF
 REGULATIONS AND PERMIT REQUIREMENTS WHICH DIRECTLY
 AFFECT THE DEVELOPMENT AND INSTALLATION OF WATER AND
 WASTEWATER UTILITIES WITHIN THE CITY. PLEASE SEE
 DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS AT THE LINK
 BELOW: HTTP://WPB.ORG/CMSPAGES/GETAMAZONFILE.ASPX?PATH=
 ~\WPB_WEBSITE\MEDIA\ENGINEERING\DEVELOPMENT-APPLICATION
 -FULL-PACKAGE_2016.PDF&HASH=7BD4DD7EB6115181D8C5977BCC0
 2A97B1960045731D3658206F27451722716EF
 THIS AND OTHER RELATED ENGINEERING DOCUMENTS CAN BE
 FOUND HERE: HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBL
 IC-WORKS/FORMS,-PERMITS-APPLICATIONS
 2. CODE OF ORDINANCES, CITY OF WEST PALM BEACH,
 FLORIDA, CODIFIED THROUGH ORD. NO. 4183-08, ADOPTED
 SEPT. 22, 2008. (SUPPLEMENT NO. 18)
 CHAPTER 90 UTILITIES, ARTICLE I. SEC. 90-7.
 POLICY REGARDING EXTENSION OF WATER OR SEWER SERVICE
 FACILITIES OF THE CITY.
 THE WATER AND WASTEWATER SERVICE AGREEMENTS AND THE
 CONSTRUCTION PERMITS ADDRESS RESERVATION OF CAPACITY
 BASED ON USAGE, METER SIZE AND FEES, DESIGN STANDARDS,
 BACKFLOW PREVENTION, FIRE SERVICE AND IRRIGATION.
 3. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, REFER TO THE LINK BELOW:
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
 4. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS
 OF ALL WATER, STORMWATER, AND SANITARY AND SEWER LINES,
 INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND
 SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES,
 METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE
 SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING
 GRADES, PIPES SIZES, MATERIALS, ELEVATIONS,
 ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL
 INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER
 LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN
 VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS.
 PLEASE SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL
 EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT,
 INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES LOCATED ON THE
 RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL
 UTILITY CROSSINGS.
 5. CUT AND CAP UTILITIES NOT IN USE, AND REMOVE ANY
 ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM CITY
 RIGHT OF WAY.
 6. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE
 DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB
 DEVELOPMENT APPLICATION).
 7. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED ADDITIONAL DEMANDS FOR WATER & SEWER (AVERAGE,
 MAXIMUM AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS
 SHALL BE PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008
 FOR WATER.
 8. SHOW VERTICAL DATUM AND DATUM CONVERSION INFORMATION
 (NAVD 88 AND NGVD 29) ON ALL SHEETS.
 9. PLEASE PROVIDE CALCULATIONS OF EXISTING AND REVISED
 PERVIOUS AND IMPERVIOUS CALCULATIONS FOR THE PROPOSED
 IMPACTED AREAS.
 10. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 11. PROVIDE UTILITY EASEMENTS TO ALLOW ACCESS FOR CITY
 PERSONNEL TO PROPOSED UTILITIES INCLUDING WATER METERS.
 12. PLEASE PROVIDE 10 FT. MIN. HORIZONTAL CLEARANCE
 BETWEEN PROPOSED WATER AND SEWER LINES.
 13. PLEASE PROVIDE INLET ELEVATIONS AT ANY PROPOSED
 MANHOLES.
 14. SPECIFY EXISTING SANITARY LINE MATERIAL IN RIGHT OF
 WAY.
 15. PLEASE SHOW VALVE SIZES AND LOCATIONS.
 16. LABEL WATER LINES AS PRIVATE WHERE APPLICABLE.
 17. PLEASE PROVIDE PROJECT ADDRESS ON PLANS.
 18. PLEASE ADD AND OR UPDATE CITY OF WPB STANDARD
 DETAILS.
 19. PLEASE CLARIFY LOCATION OF PROPOSED GENERATOR OVER
 EASEMENT ? MAY BE IN CONFLICT WITH EXISTING CITY WATER
 MAIN.
 20. PROPOSED DRIVEWAY CONNECTING TO NORTH PARCEL MAY BE
 IN CONFLICT WITH EXISTING CITY WATER MAIN.
 21. SHOW WATER MAIN IN EASEMENT THAT COULD BE IN
 CONFLICT WITH PROPOSED STORM ADJUSTMENTS.
 22. WILL DRIVEWAY BE GATED? PLEASE SHOW GATE DETAILS,
 FOOTPRINT/LAYOUT/DIMENSIONS ETC.
 23. PLEASE PROVIDE ADDRESS ON COVER SHEET.
 24. FOR FORMAL ENGINEERING SUBMITTAL , PLEASE INCLUDE
 LATEST CITY OF WPB STANDARD DETAILS IN PLANS.
 25. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES
 OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS.
 26. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 27. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY
 ELEVATIONS AT MANHOLE TIE-IN.
 28. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE Z PERMIT NUMBER IN ALL CORRESPONDENCE.
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
  
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 DIRECT: (561) 494-1098 [email protected]
  